Project update

25 May 2020

Story
 
 

 
Story

Philpotts Road closes for one day

On Friday 29 May from 7am to 7pm, the left-out lane from Philpotts Road onto QEII Drive will be closed to all traffic while we complete the road surfacing at this new intersection.

While the Philpotts Road intersection is closed, you can either use Innes Road or Main North Road to access QEII Drive.

Access to the shared cycle and pedestrian path on QEII Drive will still be possible to and from Philpotts Road by following the fenced off path and signage.

This work is weather dependent, so the closure could be a day later than now planned.

The Philpotts/QEII Intersection will remain left-out only onto QEII Drive until early July.  At this time we switch traffic onto the new QEII Drive lanes and the Philpotts/QEII Intersection will be left-in and left-out permanently.

Read more

Story
 
Image

 
Story

Winters Road East to re-open

From early morning Wednesday 3 June, the original entry point to the Winters Road cul-de-sac east of the new motorway, that gives access to our site office, is open again, left in and out only. 

Read more

Story
 
Image

 
Story

Reminder - Night work at Tram Road and Off-ramp

Nightly from Sunday 24 May to Friday 29 May 8pm to 5am, we will be installing ducts under Tram Road for future traffic signals.

The Tram Road southbound on-ramp will be closed each night and traffic using Tram Road will be managed with stop/go controls. Expect delays of up to five minutes on Tram Road.

Tram Road traffic wanting to access the motorway southbound will need to divert to Main North Road.

During the work there is no right turn from the Tram Road off-ramp. If heading to Kaiapoi please use the Ohoka Road exit.

During this night work there will be a temporary 30km/h speed limit.

More information here

Story
 
Image

 
Story

Cranford/Innes Intersection - CNC work finished and new signals up and running!

Thank you once again to all residents and businesses in this area for your understanding and patience especially during our night time work. 

Story
 
Image

 
Story

CNC bridges looking south

Story
 
Image

Image

Image

Image

Image

Image

Image

 
Story

1. Main North Road and Railway Bridges

2. Ka Putahi Creek Bridge and Shared Path Bridge

3. Belfast Bridge

4. Radcliffe Bridge

5. Styx River Bridge and Styx Shared Path Bridge

6. Prestons Bridge

7. QEII Bridge

Story
     

 
Story

Tell a friend

Please feel free to forward this email to others who may be interested or affected. 

Story
 

 
Story

Questions and Feedback

Hello everyone

We all really enjoy the feedback, comments and questions we get about the CNC project. If you wish to get in touch you can email me at melanie.williams@cncalliance.co.nz or info@cncalliance.co.nz

You could also take a look at our Frequently Asked Questions webpage. Or your question could be answered in one of our Videos.

Story
 

 
Story

Kind regards

Melanie

Story
 
Image

 
spacer

More information

spacer
 
 
Story

For more information on the Christchurch Northern Corridor project, visit our website www.nzta.govt.nz/CNC