Project progress
Activities next week (25 October - 1 November)
Please note that these works are weather dependent and may be delayed.
During the day (from 7am to 6pm)
Zone 1 (from Pukaki Creek Bridge to East of Campana Road)
-
Asphalt paving on the existing carriageway between Waokauri Bridge and Campana Road intersection
-
Complete instalment of TL-4 concrete barriers in the west of Campana Road
-
Stormwater drainage is being laid on both sides of the road between Pukaki Creek Bridge and the airport viewing platforms.
-
Installation of wire rope barrier from the viewing platforms to Orrs Road
-
Base preparation for kerb and channel at the Aviation Security entrance.
-
Fence realignment north of Campana Road
-
Erosion and sediment controls on the north side of the site
-
Streetlight cable pull between Orrs Road and Campana Road intersection
Waokauri Bridge
-
Temporary bridge support structures have been set up and the first two sections of the pedestrian steel bridge is being welded and painted.
Zone 2 (from East of Campana Road to the SH20 interchange)
-
A big push to finish drainage lines, both new and redesigned, along Zone 2 parameters
-
Placing of SIL and subsoils with box cuts
-
Continuing installation of subsoil drainage and combined service ducts
-
Continuing laying of AC28 asphalt in front of Manukau Memorial Gardens
-
Preparation for laying of AC28 between Waokauri Bridge and Manukau Memorial Gardens.
Utilities (throughout the site)
-
The common service trench crew continues laying the new service ducts and the plan is to complete the section between the Manukau Memorial Garcen entrance and the SH20 interchange by the end of October.
-
Chorus will be working to change the fibre network between Manuakau Memorial Gardens and the SH20 interchange by the end of the year.
-
Vector has booked a power shutdown on 27th October for the new cable crossing in the area close to SH20 interchange. Vector will notify the customers affected.
At night (all zones from 9pm to 5am, Sunday to Thursday)
No night works scheduled next week. However, some work that will not affect the main carriageway may occur.
People on foot and on bikes and residents will still have access should these works take place.
Safety
SH20B has introduced the following safety measures to protect all road and shared path users including two temporary signalised road crossings for people on foot and on bikes:
-
All traffic must turn left both into and out of properties and side roads. Manukau Memorial Gardens is exempt from left-turn movements
-
Vehicles turning into driveways and side roads on the southern side must watch for bikes and foot traffic on the temporary shared cycle and walking path
-
Night time detours will likely be in place from Sunday to Thursday between 9pm and 5am. Please follow the posted detour routes
-
The speed limit for SH20B is 50kph from Manukau Memorial Gardens to Tom Pearce Drive, except at crossing points and coned paving areas where the speed will briefly drop to 30kph. Please drive safely and allow extra time for your journey.
Looking Ahead
An ongoing comprehensive programme of night works is in place to enable trenching for utility services and ducting at multiple locations across SH20B. Posted detours will be in place. We apologise for any inconvenience and thank you for your patience.
Please drive safely and allow extra time for your journey.
|