A big milestone for Brougham StreetIt’s been just over a year since the first sod was turned on the Brougham Street Upgrade in July 2025, and now another big milestone is here, with the new pedestrian and cycle bridge ready for use. On Tuesday 24 November, children from Addington Te Kura Taumatua and Te Kura o te Ngākau Tapu Sacred Heart School will make the first crossing following an informal blessing at the bridge. The bridge will then open for everyone to use in the early afternoon. Opening the bridge doesn’t mean everything around it is finished. Landscaping, final road work and a few finishing touches will continue over the next few weeks. But there’s no reason to keep the bridge closed while we finish that work. We want people to be able to use it as soon as possible and have a safer way to walk, cycle or scoot across busy Brougham Street. One of the biggest moments in the bridge build came in June, when the 37 metre bridge truss was lifted into place over Brougham Street. Since then, the ramps, walking and cycling surfaces, glass panels, roof and other parts of the bridge have taken shape. This part of the Brougham Street Upgrade remains on schedule to be completed by the end of January, as planned. For now, though, it’s great to reach the point where the bridge can start doing what it was built for, helping people get safely from one side of Brougham Street to the other. |
||
![]() |
![]() |
||
Brougham Corridor work starts Monday 11 JanuaryFrom Monday 11 January 2027, we’ll begin the Brougham Street corridor upgrade. Construction will progress in sections along Brougham Street, from Collins Street east towards Brisbane Street, with each section carefully staged to maintain access and keep traffic moving. The first stage of work will begin in the centre of Brougham Street between Collins Street and Antigua Street. This will include work on underground services, tree removal and removal of the existing central median. Completing this work first will create the space needed to shift traffic before construction moves to the northern and southern sides of the road. |
||
Selwyn Street intersection
As part of this first stage of works, we need to do a significant amount of work at the Selwyn Street/Brougham Street intersection. Our intersection upgrade will follow the Council’s wastewater work at this intersection. Before the signal upgrades happen at this intersection, we need to upgrade electricity and fibre cables, stormwater pipes, and install underground ducting for the new traffic signals. Once that work is done, the intersection will be widened to allow for the T2 lanes and additional turning bays, and we will install new lighting, traffic signals, kerb and channel and line marking for the T2 lanes. There will be changes to how traffic moves around the Selwyn Street intersection. We’ll provide more information before these changes happen, so people know what to expect and can plan their journeys. |
||
![]() |
||
Community drop-in session:Come along and chat with the project team about the second stage of the Brougham Street upgrade. Find out what to expect during construction and ask any questions you may have.
Date: Wednesday 9 December 2026 We look forward to seeing you. |
||
![]() |
||
Changes to Kipling Street, Barrie Street, James K Baxter Place and Bolton AvenueAhead of longer-term changes to cul-de-sac Kipling Street, Barrie Street James K Baxter Place and Bolton Avenue, temporary barriers will be installed to prevent vehicle access to and from Brougham Street. This will help stop these local streets, which aren’t designed for high volumes of traffic, from being used as shortcuts while the work at the Selwyn Street intersection is underway. The barriers will remain in place until work begins to build the permanent cul-de-sacs, which form part of the consented project design. We will provide residents in these streets with more details before the work starts. |
||
![]() |
||
Brougham Street will remain open during constructionTo make Brougham Street better, we need to do significant work at most major intersections including Selwyn Street, Antigua Street, Montreal Street, Durham Street, Colombo Street, and Gasson Street. Keeping people and goods moving during construction is a key priority, but there will be disruption around our work areas. Brougham Street is an important freight route and one of Christchurch’s busiest roads, carrying more than 45,000 vehicles a day. To manage this, we’re carefully staging work so we can minimise the overall disruption to residents, businesses, commuters, and freight, with access to businesses and homes maintained wherever possible. Christchurch City Council is upgrading water and wastewater pipes along Brougham Street, with water supply upgrades at Barrie, Kipling and Scott Streets. We’re coordinating the Council’s upgrades with our road work so we can deliver the work efficiently and reduce overall disruption to residents, businesses and people travelling through the area. When our construction starts from Monday 11 January 2027, this will mean:
What people can expect
Keeping you updated We’ll deliver detailed work notices to businesses and residents affected by the work which will include information about what to expect and any changes to traffic management. As work progresses, we’ll continue to provide updates on upcoming work and changes to temporary traffic management to help you plan ahead. |
||
![]() |
![]() |
||
|
The crew hard at it on Collins Street - these images show progress from early November to yesterday. |
||