Overview of progress to date
All the work required to allow the main intersection work to progress was completed over the winter period.
This included the piping of the stock water race, the relocation of Chorus and Vodafone services, the installation of the new water mains and the undergrounding of the Orion services required for relocating other services, and the early road paving work.
We were also able to progress the new road linking Weedons Ross Rd and West Melton Rd sufficiently to be able to put traffic on it which allowed other areas of the site to be worked on.
Since spring, and with the improving weather, the team has been able to progress stormwater drainage, kerbing, lighting, removal of power poles, road paving and shared path works.
Over the last couple of weeks of the year the focus has been on getting the work site to a stage where we can make as much of the road and shared paths available as possible over the Christmas / New Year holiday period while also removing as much of the temporary traffic management as possible.
|
|