NZ Transport Agency Waka Kotahi and Marlborough state highway maintenance programme

Marlborough state highway planned roadworks

Saturday 20 September to Friday 26 September

19 September 2025


 

Kia ora and welcome

Kia ora,

Welcome to the first edition of the Marlborough state highway planned roadworks update.

This weekly newsletter will keep you informed about what’s happening across the region’s state highway network so you can plan ahead.

This summer, we’re planning maintenance work along 45 lane kilometres of state highway in Marlborough, from full rebuilds to fresh asphalt and chipseal resurfacing. It’s all part of keeping our roads safe and fit for the future.

Our annual summer maintenance programme kicks off in late September when you’ll see our crews out and about on the state highways patching, chip sealing, resurfacing, and rebuilding roads to help you get where you’re going, quickly and safely. We carry out this work during the warmer, drier months to ensure quality and durability. 

We’ll share more details about the full 2025/26 programme in the coming weeks.

Please feel free to share this newsletter with whānau and friends, anyone can sign up to stay informed.

When you’re driving through a worksite, please remember our crews are working hard to keep the roads safe, and keep you moving. Your patience and care makes a real difference.

For the latest updates on road conditions before you travel visit www.journeys.nzta.govt.nz/journey-planner

 

 

SH1 Picton to Christchurch

SH1 Kaikōura

  • The Kaikōura Hop car show event runs until Sunday 21 September. Drivers are encouraged to plan ahead and to be prepared for extra traffic in the region.

Upcoming work on State Highway 1 - from 29 September

SH1 Lindens Crossing (between Picton and Koromiko)

  • 24/7 work to rebuild the state highway at Lindens Crossing between Picton and Koromiko.
  • Monday 29 September to Friday 17 October (no work on weekends).
  • Stop/go with delays of up to 10 minutes.
  • Read our media release for more information.

SH1 Riverlands - near the truck stop

  • Various work including chipsealing, sweeping and line marking and high shoulder removal from Monday 29 September to Wednesday 8 October (no work on Sunday 5 October), 6:30am - 6:30pm.
  • Stop/go with 5 minute delays.
 

 

SH6 Blenheim to Nelson

SH6 Whangamoa Saddle

  • Resilience works resume on Monday 22 September and are scheduled for completion on Friday 28 November.
  • Work will be carried out Monday to Friday but stop/go traffic management and a 30km/h reduced speed limit will be in place 24/7 for the safety of all road users.
  • Expect delays of up to 10 minutes.
  • There are five sites to complete as part of this project, however only one site will be worked on at a time.
  • Read our Traffic Bulletin for more information.
 

 

SH63 Renwick to Kawatiri Junction

SH63 Andersons Bridge

  • Ongoing bridge replacement work following the June/July 2025 storm event.
  • Piling is complete and first abutment was poured today (Friday 19 September). The bridge abutment serves as a critical structural element at each end of the bridge, supporting the weight of the bridge and its loads.
  • Stop/go traffic management and a 30km/h reduced speed limit remains in place 24/7. 
  • Expect short delays.

 

 

More information

 
 

Please be aware that there may be other less disruptive state highway works not listed in this newsletter. 

All work is subject to weather and other unforeseen circumstances. In the event of unsuitable conditions, work will be rescheduled to the next suitable workday.

For more information on the Marlborough state highway maintenance programme, contact us at Marlboroughmaintenance@nzta.govt.nz

Visit our website www.nzta.govt.nz/sh-maintenance-programme/marlborough