There will be increased works along the length of Queen Charlotte Drive during March with multiple recovery sites under construction. These works will be under stop/go traffic management, please expect delays.
Crews have been working on the construction of a MSE (Mechanically Stabilised Earth) wall and associated drainage upgrades on Queen Charlotte Drive (approximately 1.7km from the SH6/Havelock turnoff) near Cullen Point, Mahakipawa Hill.
The closure that was in place at this location has now ended.
Last week crews drilled and installed concrete piles at the above location under the daytime construction closure. This week and next week anchor drilling and the installation of wailers will be undertaken, under stop/go traffic management.
Works to install a new culvert and repair the road are continuing, just prior to Moenui Road (when travelling from Havelock). This week culvert outlet works were completed, including wing walls and rock protection. Next week the third section of the box culvert is scheduled to be installed.
Works to realign the road and repair a slip have begun 70m past Governors Bay when travelling towards Picton. Crews have been drilling, installing anchors and laying concrete at this location. Next week preparation work for the ground beam is scheduled to be undertaken.
Works continue at a new retaining wall site, 450m past Aussie Bay. This week installation of the wailers has been carried out and backfilling works undertaken. Next week backfilling works are scheduled to continue at this location.
This week works have started 750m past The Grove Jetty, when travelling towards Picton to complete drainage upgrades and repair a dropout. Works will continue at this location next week.
The construction of two railway iron walls is being carried out approximately 1.9km and 2.1km past Tepuia Heights, on Queen Charlotte Drive when travelling towards Picton. Users of the Link Pathway will be guided through these sites by traffic management.
A third railway iron site is scheduled to start in the coming weeks, 450m before Moenui Road, when travelling towards Picton.
Please note there will be increased truck movements while these works are being carried out. Please plan ahead for delays.
Please ensure you keep to the reduced temporary speed limits when you're travelling through our worksites to ensure the safety of crews and road users. We thank you for your patience.
|