Waka Kotahi NZ Transport Agency

SH58 Safety Improvements Project Update

19 December 2025


 

 In this issue

  • Welcome and a look at what's been happening
     
  • Facts and figures - 2025 milestones 
     
  • Meet Nathan, our Moonshine site supervisor
     
  • Why are there so many road cones?
     
  • Holiday break dates 
     
  • Project contact information
 

 

Welcome to this SH58 Safety Improvement Project update

As we approach 2025’s end, let's reflect on the achievements since work began on this 2km segment from Moonshine Road to Murphys/Flightys Roads in June.

It’s not hard to imagine the current project’s like a ship under full sail – racing ahead well but steady as she goes.

There’s a lot of pressure on the teams this side of Christmas but any work completed in 2025 helps to create continuity of work in the New Year - “it’s a good goal to have, and we’re pushing along,” says a site superintendent.

From a distance, a vessel looks as if its sailing itself but get onboard, and you’ll discover a dedicated crew.   Each section has specialist skills and tasks to fulfil at different places but all are busy doing their bit to contribute to the greater good.

We understand that from the perspective of road users, there’s much activity but the shape of the road hasn’t changed that much, except for the Flightys Road intersection.

There’s been a massive amount of work this year but most of it has been below the ground surface.  In this edition, we’ll dive down and give you a glimpse of what’s going on in some of those sections.

As with most jobs, 90 per cent of the eventual success is about preparation.

That’s largely where the project team has been focused since work started in June.  When you’re disturbing ground, the various complex underground services which provide lifelines of telecommunications, electricity and water, must be carefully worked around.

Much of the area hasn’t been moved for decades and information about what’s underneath can be challenging to find.

We thank you for your continued patience while we strive to get the work done in the best and safest way possible.

Anytime subsoil is cut on a live highway, workers have to become amateur archaeologists.  It’s a given that they’ll stumble across both existing and unknown services – especially if that ground hasn’t been disturbed for decades.

This is serious, complex, and time-consuming work.  Apart from the known Chorus, Spark, and Wellington Electricity cables, workers on the SH58 site have found unknown and unmarked services that cross the highway. It’s possible some are old water feeds to and from, the former military camp.  Finding these old concrete pipes running parallel makes teams literally stop in their tracks.

When this happens, the unknown services must be investigated, scanned, to get a ‘positive id’.  This means digging or using air and water vacuuming to carefully uncover the extent of the old features.  Then decisions must be made about the find, and how it will affect installation of new infrastructure.

Threading an undergound needle

Putting new ducts into historically built-on land is like trying to thread a needle.  Even a simple task, such as putting a couple of ducts in an old space where ‘live’ fibre communication cables and water mains are – is basically working through a potential minefield.

It’s extremely risky work.  Workers well know that if one of those pipes or cables is hit, the surrounding and downstream residents and business would lose connections instantly.  Even though all known information is gathered ahead of time, until digging starts, we don’t know what’s underneath.

One of the first tasks is ‘potholing’;  a construction method used to investigate and locate underground utilities by digging small test holes, ensuring they’re not damaged during excavation. This process uses non-destructive techniques such as vacuum excavation to safely expose buried lines such as gas, water, and electrical cables.

By confirming the precise horizontal and vertical position of utilities, potholing prevents accidents, saves time and money, and ensures construction projects can proceed smoothly and safely.

Even when potholing is done every 10m, workers find that services often change direction to bypass things, such as old tree stumps.

One worker says, “everyone thinks people would have built straight back in day, but they didn't. We’ve found services that aren’t live but are very old, so they’re not picked up on scans.  And, if they’re not on any drawings, how do you know they’re there?”

The SH58 project’s work will help future-proof important infrastructure information in this area.  Once discovered, any new element found is identified and recorded.  Downer contacts the relevant service provider to the site to investigate for themselves.  They’ll decide whether what’s found is redundant, or working but an unrecorded, piece of their network.

Buried assets slow the ship

The unintended consequence from these discoveries is that once workers find something unexpected, work must stop and teams have to wait for answers before progressing. 

This ‘stop-start-stop-start’ eats into much productive time but it can’t be done any other way.  The eight work sub-sites across the project are reporting unknown finds all the time.

One staffer said, “some days are really good where nothing unknown is found, and then sometimes you hit a nightmare patch.  We realise this state highway is a spine – with bulk water mains and fibre cable crossing underneath.  These are critically important services which affect not only Judgeford but populations all the way to Porirua.”

Here the bulk water main is the line from Kaitoke to Porirua City – all that water literally comes across SH58.  Anywhere the project teams are working within one metre of the bulk water main, a dedicated person must be a hawk-eyed ‘stand-over’ because the work is such a massive risk to so many people.

 

 

Line of pipes for the pipe line

A rare chance to see the specially-created concrete pipes above ground for the twin culverts at the Moonshine site.

 

 

Facts and figures - 2025 milestones

Moonshine Roundabout

  • 4000m2 of organic site clearance
  • 1000m3 of topsoil stockpiled for reuse
  • 2000m3 of undercut due to poor subgrade, cut to waste and replaced with good rock
  • 3000m3 of fill brought from Flightys hillock
  • 150m of stormwater drainage and associated manholes and sumps
  • 250m of ducting

Moonshine to Flightys

• 8 x driven H Piles, formwork and footing pours for substructure concrete elements

Judgeford Golf Course Structures

• 18x bored piles with plunged H-piles for Judgeford Golf Course retaining wall and concrete lagging panels
• 2x bored piles for underpass extension

Bridge near Uncle Grant's driveway

• Cofferdam installation and substructure completion on both sides of the stream. Concrete footing and wall pours.

  • 1700m2 of organic site clearance
  • 800m of ducting
  • 40m of stormwater pipe


Flightys Roundabout

  • 3400m2 of organic site clearance
  • 4500m3 of cut to waste
  • 1500m3 of cut to fill from the hillock
  • 200m of stormwater drainage, manholes and sumps
  • 250m of ducting


Flightys to Transmission Gully

  • 250m of guard rail
  • Bridge fall protection barriers
  • Reinstatement of overhead lines 
  • Asphalt repairs
  • 12,000m2 chipseal throughout this section

Major milestones reached this year

• Flightys hillock removed –  a 'cut to fill' operation
• Substructures complete on bridge near Uncle Grant's driveway
• Judgeford Underpass retaining wall complete, when anchors are installed this month.
• Bridge near gold course underpass - cofferdams and driven piles complete
• Offline drainage work at Flightys roundabout compete
• Wellington Electricity power lines and EON overhead fibre lines shifted throughout the site
• Flightys to Transmission Gully chipsealing and line marking

What’s happening on the project now through to end of year 

• Asphalt at golf course (night works)
• Completion of Uncle Grant's driveway bridge's east pier concrete works (cofferdam removal early in the new year)
• Continue golf course underpass bridge's substructures
• Install grouted anchors through Judgeford Golf Course retaining wall

 

 

Say hello to Nathan – Moonshine Site Supervisor

We asked Nathan to share his insights on a day in the life of being a site supervisor on the project.

How long have you been doing this work?

I’ve been in construction for around 20 years, with a lot of that time spent as a supervisor. It’s a career that’s taken me across all sorts of jobs - from big infrastructure builds to community-focused work.

What other projects have you worked on before this one?

Some of the bigger projects I’ve had the joy of working on are Aotea Quay roundabout (by the Stadium), Transmission Gully expressway, Queenstown Airport safety improvements and most recently Thorndon Quay safety improvements and cycleway. Every job’s different – and that’s what I love about it.

Have you worked along the other construction phases of the SH58 highway?

Yes! I had a hand in some of the earlier phases of the SH58 project. It’s been really satisfying to see how each section builds on the last and how much it improves safety and traffic flow for locals and commuters.

What are some of the interesting aspects of the work here at this location?

Locals might not see it straight away, but there’s a lot going on behind the scenes. We’re working with complex terrain while keeping traffic moving safely, and coordinating a wide range of trades all while working to tight deadlines. The scale of it is impressive, and it’s all happening in your backyard.

What can a typical day look like for you?

Every day is different. I like to be at work by 6:30am – it gives me a head start before the site gets busy and allows me to drink my cuppa tea while it’s still hot!

We start with a crew meeting to make sure everyone knows the plan, and that have the gear they need. Then I keep an eye on progress and safety – this involves walking the job and spotting any issues.

There’s a lot of problem-solving on the fly, like making sure concrete gets poured before the weather turns and dealing with any equipment problems and environmental controls.

By the end of the day, I’ve walked around 12,000 steps on the site, answered 100 questions and made 20 phone calls by mid-morning.

How does your work contribute to the overall success of the project?

My role is to make sure the work on the ground happens safely, efficiently, and to a high standard. I’m the link between the project managers and the crews doing the mahi. It’s about setting the pace, maintaining quality, and creating a work environment where everyone can do their best.

What would you tell young people about supervising as a career option?

Supervising is a great pathway for anyone who enjoys working with people, problem-solving, and being outdoors.

The first step is getting experience on site to learn the ropes. Like any career – be the one who turns up on time with a good attitude, be curious and ask questions to show you’re keen. From there, you can move into leading small teams, and before you know it, you’re running sections of a job.

There are lots of opportunities if you’re willing to learn. You don’t need a fancy degree – but equally most workplaces will support you to gain necessary qualifications and grow your career. Whether it’s construction or another industry, people who can make things happen on the ground and bring others with them are always in demand.

What’s the best thing about your job?

Easy – it’s the people. Seeing a team work well together and finish a job we can all be proud of – that’s what it’s all about. Every day brings challenges, but that’s where the fun is, and the wins make it worth it.

What are your golden rules for getting the best out of the team you’re supervising?

• Respect is huge, it goes both ways.
• Communicate clearly and often, don’t leave people guessing.
• Lead by example – if I expect high standards, I have to show them myself.
• Recognise hard work, a simple thank you goes a long way.

The project managers would rely on you to get the massive amount of mahi done – right first time – it’s a big responsibility, right?

Yes, there’s a lot riding on getting it right. But it’s not a one-man show. It’s all about the team – each person playing their part. My job is to keep that machine ticking along smoothly.

Anything else that locals or road users might find interesting?

Just that we’re always thinking about the people using the road safety and minimising disruption is always top of mind. And when the project’s done, it’s something the whole community benefits from for years to come. That’s a good feeling.

 

 

Why are there so many road cones?

Sometimes we get comments about the amount of road cones we need to use.

Cones aren’t used only indicate an active work site. They’re also a traffic management measure to direct traffic flow to suit the specific situation at the time.

The traffic management on SH58 Safety Improvement Project’s Moonshine to Flightys Road phase, is set up in accordance with NZTA’s New Zealand Guide To Traffic Management. This protocol takes a risk-based approach to each site.   

Working on this part of the SH58 section is a significant risk for construction staff. There’s high volume traffic and the already narrow road shoulders offer little space for safe work areas.   

To protect our ground crews where we can’t install concrete or water-filled barriers, cones make lanes narrower.  We also reduce speed limits leading up to the active work sites; so that by the time vehicles reach the working area, they’re travelling at a low enough speed to lessen the danger passing traffic presents to road workers.

We want everyone who travels and works on the highway to be safe and get home without incident.  If you want to read the guide, you can find it online here.

 

 

Holiday break dates

The project site will be shutting down for the holiday break from Tuesday 23 December to Monday 12 January.

The site will be made safe and will be monitored throughout the break.

Downer has contingency plans in place, should any unexpected events occur.  If you need to contact the project team during this time, see information below.

 

 

Want to connect with the project team?

If you have any questions about the project work, email: 

sh58safety@nzta.govt.nz;

and keep a watch on the SH58 Project webpage:
https://www.nzta.govt.nz/projects/sh58-safety-improvements  

Just a note, if you ever need to report an emergency, incident or have an immediate concern about any highway in New Zealand, call the freephone 0800 4 HIGHWAYS or 0800 44 44 49.

Calls are handled by our national call centre and is staffed 24/7 – every day of the year.