Back to work at Bay Link
Since resuming work on the Bay Link site at Alert Level 3, we have progressed some important elements of the project.
Bayfair (northern end):
-
The relocation of a large stormwater pipe within the SH2 Maunganui/Girven roundabout (pictured below) is now complete. This 1200mm diameter pipe, which runs underneath the roundabout, was diverted to make way for upcoming ground improvements to support the Bayfair flyover.
-
Earthworks have been underway in the middle of SH 2/Maunganui Road preparing the subgrade for the construction of the permanent pavement.
-
Inclusion of an underpass for pedestrians and cyclists north of the Bayfair roundabout was confirmed during April. Technical investigations showed retaining the existing underpass isn’t possible and the current structure will be demolished, with a new one built. More information on the timings will be made available over the next month.
Baypark / Te Maunga (southern end):
-
Construction of several of the project’s Mechanically Stabilised Earth (MSE) walls is underway in the Baypark area. These will enable works to commence on the bridges over the rail line and SH2.
-
About 100m of concrete barriers have been removed from the middle of State Highway 29A (SH29A) and the location of the existing traffic lanes adjusted to enable the adjacent work zone to expand.
-
Cone penetration testing, which helps confirm the ground improvements are constructed correctly, has been completed near the Te Maunga roundabout.
-
The southern wetland, a large stormwater pond created to hold water in the event of heavy rain or flooding, is 75% complete.
-
Pavement works have begun on the new southern roundabout which is visible to traffic heading east along SH29A.
We are pleased to see our project neighbours, including those at HomeZone and Bayfair, resume trading after the COVID-19 lockdown and encourage you to support these local retailers.
Please continue to drive with care through the project site.
|
|