SH1 Mangamuka Gorge slip repairs – October Update
Kia ora koutou,
We have had an amazing month with more settled weather over the last couple of weeks meaning we have been able to maintain momentum and make significant progress.
We have achieved 2 significant milestones over the last 3 weeks with the piling on A5 and A12 being completed. We still have to complete the installation of the lagging walls, capping beams, and ground anchors, but the completion of the piling means that the most technical part of the repairs is now complete for these slips. The large piling drills and cranes used to install the piles can now be moved to the next site.
With the Spring weather, ground conditions continue to stabilise. However, we are remaining vigilant and prepared for whatever the unpredictable Te Tai Tokerau weather may throw at us. With a potential hot and dry summer ahead we are now making sure we are prepared with the management of hot works and minimising the risks of fires caused by the activities onsite.
We are constantly looking at ways we can safely improve our programme, however we are still anticipating the road to re-open in late 2024.
We appreciate your continued understanding, patience, and support.
|