State Highway 20B Early Improvements Update

22 January 2021

Kia ora koutou,

State Highway 20B Project Updates keep you up-to-date with project progress and upcoming physical works on State Highway 20B (SH20B).

Story
 

 
Story

Night time Stop/Go Traffic Control for SH20B

No more full road closures are planned for night works on SH20B.

From next Sunday 24 January, between 9pm and 5am, Sunday to Thursday nights, we will have Stop/Go Traffic Control and traffic lights in place along SH20B.  This will mean that the new electric Airport Link bus service, along with all vehicles, will have access, every night, along SH20B between the SH20 Interchange and Auckland International Airport.

However, as we are still working on the road, there may be delays as we are move plant or stop work to let vehicles through. Please allow extra time for your journey.

Story
 

 
Story

Project progress

Activities next week (24 - 31 January)

Please note that some works are weather dependent and may be delayed.

During the day (from 7am to 7pm)

Zone 1 (from Pukaki Creek Bridge to East of Campana Road)

  • Install additional streetlight ducting near Pukaki Creek Bridge
  • Pour sloped channel at the northern aircraft viewing platform
  • Prepare and pour footpath behind existing guard rail near Pukaki Creek Bridge
  • Continue placing the shared use path near the aircraft viewing platform from Pukaki Creek Bridge to south of Campana Road.
  • Continue placing street lights on the north side from Pukaki Creek Bridge to Orrs Road
  • Continue signal works near Campana Road
  • Install street light ducts at Campana north-west with drainage crossing extension
  • Place kerb at Campana Road on the north-east and on the northern side at Orrs Road
  • Pour concrete subbase near the Aviation Security Gate
  • Start verge backfill and kerb preparation near Orrs Road
  • Start laying cut off drains between the aircraft viewing platform and Orrs Road on the north side

Waokauri Creek Bridge

  • Southern transition barriers are being finished
  • Various works around in the site in preparation for railing installation

Zone 2 (from East of Campana Road to the SH20 interchange)

  • Continue installation of the shared use path underneath the SH20 overpass
  • Begin vehicle crossing  realignment works at Bowers Masonry 352 – 356 Puhinui Road
  • Locate and protect the gas main opposite Manukau Memorial Gardens westbound via hydro vac
  • Continue current drainage lines work opposite Manukau Memorial Gardens
  • Continue drainage works near the Black Bridge Nursery Puhinui Road entry
  • Vehicle crossing construction works at night at 437 and 467 Puhinui Road
  • Continue widening works and guardrail installation near Prices Road 

Utilities (throughout the site)

  • Service ducts will be laid between Prices Road and the SH20 Interchange 
  • Street ducting will be completed from east of Campana Road up to the Waokauri Creek Bridge.

At night (all zones from 9pm to 5am, Sunday to Thursday)
 

The road will be OPEN to through traffic, but STOP/GO traffic controls and traffic lights will operate.

Please drive safely and allow extra time for your journey

  • Asphalt pavement replacement continues along the existing carriageway between Pukaki Bridge and SH20
  • Vehicle crossing widening at 467 Puhinui Road
  • SH20 under-bridge Shared Use Path works

Safety

SH20B has introduced the following safety measures to protect all road and shared path users including two temporary signalised road crossings for people on foot and on bikes:

  • All traffic must turn left both into and out of properties and side roads. Manukau Memorial Gardens is exempt from left-turn movements
  • Vehicles turning into driveways and side roads on the southern side must watch for bikes and foot traffic on the temporary shared cycle and walking path
  • The speed limit for SH20B is 50kph from Manukau Memorial Gardens to Tom Pearce Drive, except at crossing points and coned paving areas where the speed will briefly drop to 30kph 

 

Story
 

 
Story

Contact us

Please call us at 0800 796 796 or email sh20B@nzta.govt.nz if you have any questions about the SH20B Early Improvements project.

Story
 

 
spacer

Project overview

spacer
 
 
Story

Waka Kotahi NZ Transport Agency and Auckland International Airport Limited are upgrading State Highway 20B for better and more reliable travel options with a new shared path and additional priority lanes between Pukaki Creek Bridge and State Highway 20.

This project will integrate with improved transport facilities within the airport precinct along SH20B and at the upgraded Puhinui Station Interchange.

The project is the first step of the Southwest Gateway programme to provide better public transport, walking and cycling facilities with safer and more efficient freight movements to, from and around Southwest Auckland.

Fulton Hogan undertakes this work on behalf of Waka Kotahi.

Key early improvements on State Highway 20B to be delivered by 2021 include:

  • A safe place for people to walk and ride bikes
  • Safety improvements including central median barrier protection, improved lighting and a reduced speed
  • Improved pavement, drainage and stormwater treatment
  • Two improved intersections at Campana Road and Manukau Memorial Gardens.

Waka Kotahi NZ Transport Agency works to create transport solutions for all New Zealanders – from helping new drivers earn their licences, to leading safety campaigns to investing in public transport, state highways and local roads.

For more information on the project, you can also visit our website at www.nzta.govt.nz/projects/southwest-gateway/20connect/

Story