Construction update
The project is on schedule to be complete and opened in mid-2023.
Phase 1 of work around the Petone train station saw the re-surfacing, new kerbing and car park layout completed in early 2022. Works are still progressing on the station upgrade, alongside a new ramp and stairs in the area. The final layout work for the car park is set to be completed in February.
The main cycleway route is progressing well with fencing, lighting and CCTV underway. Portions of the cycleway have already been completed with asphalt, fencing and lighting installed.
All structural work on underpasses is complete, with finishing works, utilities services and surfacing remaining. It was great to complete the installation of 200 facing panels that run along the underpass ramps plus necessary structural works before Christmas.
A new crossing was installed at Marsden Street and new street layout works are underway at Bridge and Marsden streets.
Coming up in 2023
We're excited to enter the final stage of the project. As our on site team return for the New Year, the focus is on:
-
completing fencing, kerbing, and cabling works
-
installing any remaining lighting and CCTV, plus
-
laying the final pavement.
Check out the snapshots below to see our progress so far.
|