View online |
![]() |
![]() |
O Mahurangi project update |
![]() |
![]() |
19 June 2025 |
![]() |
![]() |
Crack showing ground movement at the largest fill site on the project, Fill 9 where the future Ara Wēiti connection/Link Road 2 will be located. Programme delayA slip at the largest fill site on the project on has delayed construction to the Stillwater and Ara Wēiti section of the road. While we are still working to understand the full impacts, the project will now open as a single completed corridor instead of the staged opening previously planned. The overall project timeline is still on track for completion in 2028.
What has happened? Due to the slips continued movement, emergency works were declared in March to allow remediation works to be undertaken sooner. This minimises the risk of the slip damaging existing assets and private property.
Why has this caused a delay?
How will this impact me?
What have you done since the slip was observed? Have a look at our FAQs here for more information on how we are addressing this. https://www.nzta.govt.nz/projects/penlink/frequently-asked-questions/ |
![]() |
![]() |
||
![]() |
Event flyer Stillwater information eventWe know this change to the staged opening will be frustrating for the community, especially residents in Stillwater and Ara Weiti. We will be holding our next inforation drop-in evening at the Stillwater Boating Club on Wednesday 23 July from 4-7pm. Please come and ask the team any questions on our upcoming works and changes to the programme. |
![]() |
![]() |
SH1 bridge What's happening in July
State Highway 1 and Ara Weiti Road The earthworks team is continuing the cut to fill operation on the on- and off-ramps for SH1. Along Ara Weiti Road work progresses on the road widening, installation of the precast concrete panels on the bridge at Link Road 1 and construction of the retaining wall by Link Road 2.
Stillwater Early July there will be a temporary river closure, please see below for more details.
Whangaparāoa |
![]() |
![]() |
||
![]() |
Weiti River Bridge Wēiti River bridge progressThe western side abutment of the Wēiti River bridge is completed and the two land-based piers are at their final height. An additional 2 in river piers are currently being constructed. Upcoming river closure July will see the last of our three months of temporary Wēiti River closures, to ensure safe and continuous supply of concrete for the Pier 4 pile cap. The final closure is from From 5pm Monday 7 July to 9am Wednesday 9 July. The channel closure does not affect vessels navigating the river downstream of the worksite.When the work is complete, we will reopen to the 18-metre-wide navigable gap for vessels to pass through. We apologise for any inconvenience caused and thank all river users and neighbours for their patience during the ongoing construction of the new Wēiti River Bridge. Should you have any questions regarding this closure, please don’t hesitate to contact us. |
![]() |
![]() |
More informationFor more information on the O Mahurangi project, contact us at omahurangi@nzta.govt.nz or by calling 0800 7365 465. Visit our website www.nzta.govt.nz/penlink. |
![]() |
|
|