State Highway 20B Early Improvements Update
11 September 2020
Kia ora koutou,
State Highway 20B Project Updates keep you up-to-date with project progress and upcoming physical works on State Highway 20B (SH20B).
Activities next week (6 - 13 September)
Please note that these works are weather dependent and may be delayed.
During the day (from 7am to 6pm)
Zone 1 (from Pukaki Creek Bridge to East of Campana Road)
-
Earthworks and subgrade improvement placement between Orrs Road and Waokauri Bridge
-
Vector gas service protection works at Orrs Road
-
Installation of network storm water drainage and subsoil drainage from Orrs Road to Waokauri Bridge and at Aviation Security gate.
-
Deep lift asphalting pavement widening on the south side of the alignment between Orrs Road and Campana Road.
-
Asphalt overlay and partial depth pavement reconstruction between Pukaki Creek Bridge and Orrs Road
Waokauri Bridge
-
Pier headstock construction
-
Ongoing demolition of the existing bridge walkway
Zone 2 (from East of Campana Road to SH20)
-
Preparing subgrade west of Manukau Memorial Gardens entrance
-
Earthworks batter cuts approaching SH20 interchange
-
Installing network drains in front the Manukau Memorial Gardens
-
Filling operation to the east of the surcharge
-
Installation of drainage between Prices Road and Manukau Memorial Gardens
Utilities(throughout the site)
-
Targeted completion of common service trenching between Orrs Road and Campana Road
-
Working with Vector looking to install the new transformer at the end of month and livening the new cables between Orrs to Campana in mid-October
At night (all zones from 9pm to 5am under either stop/go or full road closure traffic management)
-
Exploratory works will continue beneath the existing road to verify the location of existing services at numerous locations
-
Saw cutting of the existing road for new drainage crossings will continue
-
Trenching works for ducting and drainage crossings at multiple locations throughout the site will be ongoing
-
Night time paving works across the existing road with localised adjustments to the traffic management arrangements
SH20B has introduced the following safety measures to protect all road and shared path users including two temporary signalised road crossings for people on foot and on bikes:
-
All traffic must turn left both into and out of properties and side roads. Manukau Memorial Gardens is exempt from this
-
Vehicles turning into driveways and side roads on the southern side must watch for bike and foot traffic on the temporary shared cycle and walking path
-
Night time detours will likely be in place from Sunday to Thursday between 9pm and 5am. Please follow the posted detour routes
-
The speed limit for SH20B is 50km/hr from Manukau Memorial Gardens to Tom Pearce Drive. Please drive safely and allow extra time for your journey
Looking Ahead
An ongoing comprehensive programme of night works is in place to enable trenching for utility services and ducting at multiple locations across SH20B. Posted detours will be in place. We apologise for any inconvenience and thank you for your patience.