Huntly section update October 2016
   

Some very big machinery has been arriving at the Huntly site as the contractors gear up for their second season of earthworks.
In their first season, between Ocotber and May, the Fulton Hogan-HEB Joint Venture moved about 600,000m3 but the target this season is 2 million m3.
At peak this summer there will be more than 150 machines along the 15.2km site, including a 180-tonne excavator which can handle 25 tonnes in its giant bucket. That's it pictured here dwarfing stakeholder manager Trish Viall.
The focus over winter has been bridges – with good progress made on five of the nine bridges.

Read more about what’s happening on the Huntly section in the latest project update here

 

 

Story
 
Back to top
 
Info For general enquiries or contact information about the Waikato Expressway please visit our website www.nzta.govt.nz/waikato-expressway or email waikatoexpressway@nzta.govt.nz or ‘like’ us on Facebook.
 
Twitter Facebook YouTube
 
 
 
© 2009 – 2015 NZTA. All rights reserved. Privacy Policy | Legal disclaimer | Copyright

You have received this email because of previous communications with the NZ Transport Agency. If you no longer wish to receive these emails you can choose to unsubscribe here

If you received this email from a friend, sign up to receive this newsletter
New Zealand Government