View online |
![]() |
![]() |
O Mahurangi |
![]() |
![]() |
31 January 2025 |
![]() |
![]() |
Future highway alignment heading towards the Whangaparāoa intersection. Whangaparāoa updateOur work at the Whangaparāoa section of the project is progressing well with the majority of the bulk earthworks now complete between the Wēiti River and Whangaparāoa Road. In mid-2024, we began the relocation and installation of underground services that will enable our team to move to the next phase of works, as we continue the construction of the main alignment for the future Whangaparāoa intersection. The upcoming, long term temporary closure at the Cedar Terrace intersection is expected to happen in March and be in place for at least 12 months. During this time, all Cedar Terrace traffic will be detoured via Scott and Norfolk Roads. We will also be installing temporary steel roadside safety barriers along Whangaparāoa Road next to our work site to ensure our team has a safe working space, while maintaining two lanes of traffic. |
![]() |
![]() |
Pier 4 second pile concrete pour under way earlier this week. Large concrete pour successfully completedWith the successful concrete pour for the Pier 4 piles, the Wēiti River channel has been reopened. While the channel is open, vessels travelling upstream of the worksite will pass through a restricted navigable gap between the eastern and western sections of the temporary platform. During our working day as construction continues, loads will regularly be lifted over the navigable gap requiring the channel to be intermittently closed for short durations at these times. This is to keep all river users safe and ensure no vessel passes beneath a suspended load. We ask all vessels to notify the project via VHF CH73 or 0800 PENLINK and our project team will direct you accordingly via safety vessel and/ or hand signals. |
![]() |
![]() |
Survey team: Left to right - back row: Ed, Roshan, Ahmad, Wesley; front row: Brenda, Ihor, Matthew. Staff spotlight: Survey TeamThe Survey Team are responsible for the collection of data across the project using specialist equipment. They work with the Construction and Design Teams to ensure that what is being built on site is consistent with the design drawings and specifications. This is done by accurately transferring the design information on to the ground for the Construction Team, ensuring they build in the correct position and to the correct levels. The Survey Team are responsible for carrying out as-built surveys and producing the final as-built drawings. As-built is a term used in construction that is standard practice to accurately record the final drawings of a project and show what was built. The team:
|
![]() |
![]() |
12 months of changeThe photos below show changes happening across our site, from November 2023 to November 2024, with each comparison image taken from the same location. |
![]() |
![]() |
![]() |
More informationFor more information on the O Mahurangi project, contact us at omahurangi@nzta.govt.nz or by calling 0800 7365 465. Visit our website www.nzta.govt.nz/penlink. |
![]() |
|
|