Project update

29 July 2019

Story
 
 

 
Story

QEII Drive further piling and wall reconstruction

From next week, we will be removing the wall panels for the QEII Drive bridge abutments. This is so further piling work can happen. After the piling work is complete, we will reconstruct the wall panels and start building the bridge.

Because some of this work is close to QEII Drive we need to work at night, stopping traffic on QEII Drive in both directions for about five minutes at a time as each panel is removed. We plan to start the night work on Wednesday 7 August and expect to be finished by 16 August.

Additional ground improvements (piles) are needed because the ground conditions along QEII Drive have proven to be even worse than expected. Adding more piles now will ensure this structure is resilient and will last.

More information about this work here.

Story
 
Image

 
Story

Lane closures on SH1 southbound - Sunday and Monday nights

Further work to widen SH1 southbound between the Waimakariri Bridge and the Western Belfast Bypass is about to get underway. To do this we need to install steel safety barriers and prepare the site for the earthwork crews. The right side southbound lane on SH1 will be closed between 6pm till 5.30am on Sunday night 4 August and possibly Monday night 5 August.

Read more here.

Story
 
Image

 
Story

New Video

Check out our latest video where Kirsty our Traffic Manager talks about her role and how we keep everyone working or driving on the road safe.

See this and other videos on our website's video tab

Story
 
Image

 
Story

Tell a friend

Hello everyone

Do you have friends who would be interested in this info? Please feel free to forward this email to them. 

Story
 

 
Story

Kind regards

Melanie

Story
 
Image

 
spacer

More information

spacer
 
 
Story

For more information on the Christchurch Northern Corridor project, visit our website www.nzta.govt.nz/CNC

Story