Road layout changes near Portland Road next week
Next Wednesday night, temporary steel barriers will be installed along SH1 either side of Portland Road, traffic lanes will be shifted westwards, access to Loop Road (south) will be stopped and a changed intersection priority put in place at the Portland Road intersection.
Shifting the traffic westwards will provide space to construct the new left turn slip lane into Portland Road and the widening works required to improve the intersection.
From 7pm on Wednesday 12 February the state highway will be reduced to a single lane under manual stop/go traffic control to enable the barriers to be installed and road layout changed.
From 6am Thursday morning, the new road layout will be in place and the intersection of Loop Road (south) and SH1 will be closed.
Access to Otaika Valley and Mangakahia will be via SH15 at Loop Road (north). Pedestrians and cyclists can still access Loop Road (south) from SH1, as a safer alternative than travelling though the construction area on SH1.
Construction programmes can change at short notice due to unplanned events and weather. If the nightworks do not occur as planned on Wednesday night, the contingency date for these works is Thursday 13 February.
Changes at Portland Road
A haul road will be constructed across Portland Road and there will be periods of stop/go traffic control to allow earthworks to be transported across the road.
To slow traffic approaching the haul road on Portland Road, left turn movements into Portland Road will be required to give way to SH1 traffic turning right into Portland Road.
A right turn bay will be installed on SH1 to improve safety for turning traffic.
Please slow down travelling though the area as contractors are working close to the road.
|