SH4 Site Update
1. Te Oreore Underslip
This section continues to operate with a 30km/h speed limit. Instrument monitoring and reporting for the site has continued.
Construction of three of the five dewatering wells has been completed.
2. Raukawa
Over the period of lockdown, the Ruapehu and Whanganui District Councils were unable to accept consent applications. While councils are now back operating, there are delays expected to this process due to a backlog of applications. However, planning, design and property purchase is continuing to progress.
3. Whiskey’s Corner
There was a minor weather-related delay to finishing work inside the barrier at this site, but we’re expecting to be completed this week.
We will finish sealing the road in spring to avoid ‘pavement failures’, which means cracking, or potholes, which would be more likely if we did this work in winter.
4. South Raupiu Retreat
Around 40% of the work on this site has been completed, with most of the remaining work likely to be completed by August. Work on the surfacing will be completed in spring which is a much better time of year to do this than mid-winter.
5. Otoko Pā Overslip
All work on this site has been completed.
6. Hapokopoko Curve Rock
A hui took place for this site last week, to mark that physical work will be starting soon. Please expect delays on this day as traffic will be reduced to one lane.
7. Kukuta Underslip
The site remains under one-way traffic lights.
The project’s design work has nearly been completed and consent is in place.
|