Key milestones
A number of events have impacted the project's programme of works over recent months such as COVID19 and unusually wet weather.
These events have resulted in a new timeline and we would like to share new key milestone dates with you. Please know that these dates were identified before Northland entered COVID19 Alert Level 2 and may need further adjustment.
Currently the project team plans to meet the following timeline:
Late August - the side barrier and footpath on the eastern side of the bridge will be constructed.
Late September - the traffic island on the bridge will be finished, and the traffic lights will be installed and activated.
Early October - the shared path under the bridge will be finished.
Mid October - the project will be completed.
|