Rolleston Access Improvements Project Update |
6 June 2024 |
Design underway for Rolleston Access ImprovementsWe’ve updated our plans for improving access and efficiency around SH1 Rolleston. This follows on from the investigations and public consultation carried out during the project business case, which wrapped up in late 2023. The main features of the design are:
The design stage prepares the project for construction. This includes working through the planning and consents process, as well as continuing discussions with property or business owners within the project area where access or the road layout may change. Design, consenting and property purchase is likely to take 18 months, with construction currently programmed to start in late 2025. |
||
Dunns Crossing and Walkers Roads intersection with State Highway 1 |
||
A new two-lane roundabout will be designed with a pedestrian and cycling subway/underpass under the state highway. This will connect with existing or planned shared use or cycle paths. |
||
Getting into and out of Rolleston and the Industrial Area
From Christchurch From the south The roundabout at the Dunns Crossing Road and Walkers Road intersection with State Highway 1 becomes the key southern freight route into and from the industrial area via Walkers Road People travelling to residential areas and Rolleston township from the south will turn right at the roundabout and enter via Dunns Crossing Road and Brookside or Lowes Road. |
||
Flyover and off-rampA direct flyover connecting Rolleston township with the business and industrial area will be built. The design is future proofed for growth and improves safety at high-risk highway intersections by creating left-in/left-out only at Rolleston Drive South, Brookside Road and Tennyson Street. A southbound service lane provides access to Rolleston Town Centre and businesses beside the highway. There is a free left-turn from Hoskyns Road onto the highway (over the rail crossing) and into its own lane on the motorway.
|
||
Checking for underground servicesIn June potholing will begin. This is to check for the location of underground services along the state highway and in other locations within the project area. |
||
More informationFor more information see our website and sign up for the newsletter. For specific questions email rollestonaccess@nzta.govt.nz
|
||
|
|