Westport:
11-13 Haselden Street, Westport
Construction on four single-level two-bedroom homes is underway and proceeding well. It is currently anticipated that South Peak Homes will complete these homes in June 2025, pending no unforeseen delays to the project.
Click here to see a progress picture
221-213 Palmerston Street
This site is no longer under assessment and
redevelopment plans are progressing on this site.
Kāinga Ora is proposing to build eight new single-level homes, consisting of four one-bedroom homes and four two-bedroom home. Previously we had communicated that we were looking to build eight one-bedroom homes. An amendment to the resource consent application was lodged in April 2025.
If these plans go ahead, we would be looking to deliver them by June 2026.
To view the site plan, click here
19A Russell Street
This site has changed from 'under assessment' and is now in the 'changed confirmed' phase of the project. This means redevelopment plans are progressing for this site, which will see site investigations undertaken, to help finalise a feasible design option. At this stage Kāinga Ora is exploring options that include two homes for this site. If these plans go ahead, we would be looking to deliver them by June 2026.
Greymouth:
14-16 Doyle Street, Greymouth
Brown and Son Construction 2009 Limited is currently building eight new accessible two-bedroom homes, which Kāinga Ora will take ownership of once construction is complete and agreement conditions met. It's anticipated that these homes will be completed in June 2025.
Due to a change with this contract, please note that the company that we now have an agreement with has changed from Westland Homes Limited to Brown & Son Construction 2009 Limited. We previously communicated that these homes would be built to accessible standards, however this has been changed to Full Universal Design (FUD) standards. You can find out more about FUD standards here: Accessibility at Kāinga Ora :: Kāinga Ora – Homes and Communities
Click here to see a progress picture
55 High Street, Greymouth
Kumara Junction Developments Limited is currently building four new two-bedroom homes, which Kāinga Ora will take ownership of once construction is complete and agreement conditions met. Completion is anticipated to be in mid-2025.
Click here to see a progress picture
39 Shakespeare Street,
Greymouth
Kumara Junction Developments Limited is currently building five new two-bedroom homes, which Kāinga Ora will take ownership of once construction and agreement conditions met. Completion is anticipated to be in early-2026.
Click here to see a progress picture
18
Tasman Street, Greymouth
KR Construction Limited is currently building seven new two-bedroom homes and a three-bedroom home, which Kāinga Ora will take ownership of once construction is complete and agreement conditions met. Completion is anticipated to be in late-2025.
45-51 Ward Street, Cobden, Greymouth
Redevelopment plans are progressing for this site. The resource consent application has now been lodged for this site. The eight two-bedroom homes proposed for this site will be built offsite through the Rolleston Prison Programme and transported into place after site preparations are carried out.
If these plans go ahead, we would be looking to deliver them by June 2026.
46-48 Firth Street, Cobden, Greymouth
This project is under assessment.
Hokitika:
105 Fitzherbert Street and Hampden Street
Hammer Down Developments is currently building two new two-bedroom homes, which Kāinga Ora will take ownership of once construction is complete and agreement conditions met. Completion is anticipated to be in mid-2025.
Click here to see a progress picture
132-136 Hoffman Street
This redevelopment will deliver five new homes, consisting of four three-bedroom and one four-bedroom homes. Construction on these homes is well underway, and at this stage completion is anticipated for August 2025.