Construction stages
Stage one: May – August 2023
The construction of the temporary road alignment, including a temporary roundabout at the roads' tie-in points, is underway.
Stage two: Late July/ August 2023
We will move traffic onto the newly constructed temporary roads that skirt around the construction site during the last week of July. This will include stop/go works at night. If wet weather causes delays, then this will be delayed until early August.
Stage three: August 2023 – February 2024
Earthworks and drainage, and the start of construction of the new permanent roundabout will take place. Concrete, pavement, and surfacing works will take place, and work will begin on the shared user path.
Stage four: February – May 2024
There will be further drainage, pavement and surfacing works, and final works on the shared user path will be completed.
Stage five: April – mid 2024
Further earthworks will be completed, including final pavement and surfacing works. The project is expected to wrap up by July 2024.
|