Week commencing 10 March 2019

Intended programme for next week (weather dependent, therefore subject to change)

Owens Place  A contra flow remains in place during pavement works in the verge next to HomeZone. No traffic delays are expected. Sunday 10 March to Saturday 16 March 2019.
Nights & days: ongoing.

SH2 & SH29A Truck and trailer movements through site access points to move construction plant and deliver materials. No traffic delays are expected. Monday 11 March to Friday 15 March 2019. Days: 9am to 4pm.

Owens Place A contra flow will be in place while trenching occurs across Owens Place to install cesspits. No traffic delays are expected. Wednesday 13 March and Thursday 14 March 2019.Nights: 7pm to 6am.


Advanced notice of significant works

SH29A Semi static closure required between Baypark and Te Maunga roundabouts while drilling rigs are moved. Minor traffic delays expected.  Sunday 17 March 2019. Night: 9pm to 10pm.

Matapihi Road Lane closures will be in place while the road layout is changed. Traffic will be moved onto the new section of road (southern side) between SH2 and the rail line, to enable the work area on the northern side to be extended. Minor traffic delays expected. Sunday 17 March and Monday 18 March 2019.
Nights: 7pm to 6am.

Owens Place Lane closures will be in place while trenching across Owens Place. No traffic delays are expected. Tuesday 19 March and Wednesday 20 March 2019. Nights: 7pm to 6am.

SH29A closure Closure of SH29A between the Te Maunga and Baypark roundabouts to install stone columns. A sign posted detour will be in place. Traffic delays are expected. Friday 22 March to Monday 25 March 2019. Nights and days: 9pm Friday to 5am Monday.

Long-term traffic management
• State Highway 2 between Te Maunga roundabout and Concord Avenue - narrowed lanes and a 50km/h temporary speed restriction are in place for the duration of the project.

• Bayfair roundabout – a 30km/h temporary speed restriction is in place for the duration of the project.

• Matapihi Road, adjacent to the golf driving range – narrowed lanes and a 30km/h temporary speed restriction is in place for the duration of the project.

• Girven Road, near the Bayfair roundabout - narrowed lanes are in place for the duration of the project and the right-turn from the Bayfair Shopping Centre car park onto Girven Road is permanently closed.

• Access onto State Highway 2 / Maunganui Road from Exeter Street is closed for about 18 months. Resident only access.

• SH29A near Baypark – narrowed lanes and a 50km/h temporary speed restriction are in place for the duration of the project.

Story
 

 
spacer

More information

spacer
 
 
Story

For more information on the Baypark to Bayfair Link upgrade project, contact us baylink@nzta.govt.nz

Visit our website www.nzta.govt.nz/baylink