Night works this Sunday
Between 6pm, Sunday 24 July and 7am, Monday 25 July, we'll be working to install the ducting across the intersection, to begin the process of undergrounding the overhead power supply. This work is weather dependent and may need to be rescheduled to the following night(s).
The work is being undertaken at night when traffic volumes are lower to avoid congestion and disruption. It is also safer for our work crews and road users.
The intersection will be temporarily controlled by traffic lights during these works. Please look out for our staff and follow their instructions. Footpath access around our work site will be maintained. Also, please look out for changes in traffic management and follow signs on site. A 30kph speed limit will be in place.