QEII Drive further piling and wall reconstruction
Next week we are starting the steel piling for the QEII Drive bridge foundations. We hope to have two crews, one on each side of QEII Drive installing the piles so we can get this work done as quickly as possible.
This work will be noisy and we want to thank you in advance for your continued patience and understanding.
We are installing about 220 additional piles on each side of QEII Drive. We will do this work within our normal hours of work - 7am to 7pm Monday to Saturday.
All going well, the piling will take six to eight weeks to finish and then we will reconstruct the ramps and wall. The bridge beam will be placed early next year.