Longswamp section project update - July 2018
   

The July project update for the Longswamp section of the Waikato Expressway highlights progress in the past three months – including at the Whangamarino Road overbridge.

This week the beams were hoisted into place on the western side of the bridge (pictured above) which will connect communities on each side of the expressway when it opens to traffic later this year.

Traffic has been switching on to the new south-bound lanes in recent months – and this creates room for construction of the north-bound lanes. All good signs of progress as the project remains on track to be completed in mid-2019.

Read the July project update here

Story
 
Back to top
 
Info For general enquiries or contact information about the Waikato Expressway please visit our website www.nzta.govt.nz/waikato-expressway or email waikatoexpressway@nzta.govt.nz or ‘like’ us on Facebook.
 
Twitter Facebook YouTube
 
 
 
© 2009 – 2015 NZTA. All rights reserved. Privacy Policy | Legal disclaimer | Copyright

You have received this email because of previous communications with the NZ Transport Agency. If you no longer wish to receive these emails you can choose to unsubscribe here

If you received this email from a friend, sign up to receive this newsletter
New Zealand Government