Intended programme for w/c 9 March 2020 (weather dependent, therefore subject to change)

SH2/SH29A lane closures – single lane in each direction stone column works Monday 9 March to Thursday 12 March, nights only 8pm to 5am.

SH2 near Concord Ave lane closure single lane, southbound for barrier removals Tuesday 10 March to Wednesday 11 March nights only 7pm to 5am.

SH2 near Concord Ave lane closure single lane, southbound for asphalting, Thursday 12 March night only 7pm to 5am.

SH2 & SH29A Truck and trailer movements through site access points to move construction plant and deliver materials. No traffic delays expected. From Monday to Friday 9am to 4pm.

Advanced notice of significant works

SH29A both directions Lane closure both directions for concrete barrier removal Sunday 15 March to Thursday 19 March nights only 8pm to 5am.

SH29A both directions Lane closure both directions for concrete barrier removal Sunday 22 March 2020 to Thursday 26 March nightls only 8pm to 5am.


Long-term traffic management
• SH2/Maunganui Rd north-bound signalised pedestrian crossing is installed and active for the public to cross via the underpass to Bayfair Shopping Centre.
• SH2 between Te Maunga intersection and Concord Avenue - narrowed lanes and a 50km/h temporary speed restriction are in place for the duration of the project.
• Bayfair roundabout – a 30km/h temporary speed restriction is in place for the duration of the project.
• Matapihi Road, adjacent to the golf driving range – narrowed lanes and a 30km/h temporary speed restriction are in place for the duration of the project.
• Girven Road, near the Bayfair roundabout - narrowed lanes are in place for the duration of the project and the right-turn from the Bayfair Shopping Centre car park onto Girven Road is permanently closed.
• SH29A near Baypark – narrowed lanes and a 50km/h temporary speed restriction are in place for the duration of the project.

Story
 

 
spacer

More information

spacer
 
 
Story

For more information on the Baypark to Bayfair Link upgrade project, contact us baylink@nzta.govt.nz

Visit our website www.nzta.govt.nz/baylink

Story