Lots of things are changing as work progresses on the PP2Ō Expressway project and this month’s edition is packed with information. A major project milestone was reached this month when the first new Ōtaki River Bridge beams were placed on the columns that have been constructed on the south bank of the river.
The road marking on SH1 heading into the Mill Road roundabout will change soon and the pedestrian underpass will close and be replaced with a signalised pedestrian crossing just north of the roundabout.
It’s important motorists and pedestrians pay attention and slow down to ensure everyone is safe.
Shared pathway designs are also moving forward. You’ll find some detail below as well as finding lots more information on our website www.nzta.govt.nz/pp2o
If you need any further information please call us on 0800 PP2O INFO or email pp2o@nzta.govt.nz
Ngā mihi
Andy Goldie, Project Manager
|