Coming up this month
This month we are seeing Whiriwhiritoa Bridge construction get underway (pictured below), linking Klinac Lane and Maritime Lane. We are working carefully with Ngāti Rēhia as kaitiaki of the area to protect the Whiriwhiritoa Stream (see above) and its aquatic life.
At the moment, we are busy completing kerbing and footpaths on Waipapa Loop Road, ensuring good access on and off the highway and to and from other roads at the intersection.
The new ITM fence on boundary of Waipapa Road and along SH10 will be completed this month, giving more definition to the Waipapa Road roundabout approach.
The final layer of asphalt for the project is booked for April (details below) and will bring the road surface up to its final level, aligned with the manholes and drainage on the roundabout.
As soon as the new asphalt is completed we will proceed with final line marking of lanes, road shoulders and traffic guidance.
|