Phase 4 traffic switch coming | Ngā hurihanga ki te rori e haere ake nei
News flash! We are gearing up for our next traffic switch – which will be the fourth traffic layout of the project so far.
Leading into that, all the underground works on the northbound side of the motorway are finished and we've already laid around 7,000 tons of asphalt - with approximately another 4,000 tons to go.
The switch into the Phase 4 traffic layout (see graphic below) is scheduled for late April. If you want to know exactly when it will happen once timing is confirmed, you can sign up to our weekly traffic notices by subscribing here.
Construction works during the Phase 4 layout will focus on installing the middle (and final) sections of three large stormwater box culverts crossing under the motorway between the Beach Road and Park Estate Road overbridges. These last culvert sections will connect up to and complete the sections already installed under the eastern and western sides of the motorway.
Once these culverts sections are installed, further asphalt, lane markings, streetlights and concrete barriers will complete the pavement works for Stage 1A of the project.
|