Project progress
Activities next week (18 - 25 October)
Please note that these works are weather dependent and may be delayed.
During the day (from 7am to 6pm)
Zone 1 (from Pukaki Creek Bridge to East of Campana Road)
-
The second layer of asphalt laid for road widening
-
Pavement laid at the Aviation Security area
-
Installation of kerb, channel and barrier (concrete and temporary steel) between Pukaki Creek Bridge and the Campana Road intersection
-
Preparing subgrade from Orrs Road to Waokauri Creek Bridge
-
Stock fencing will continue to be installed by Campana Road
-
Widening works at the Campana Road intersection will start
-
Stormwater drainage continues between Pukaki Creek Bridge and the Aviation Security gate.
Waokauri Bridge
-
Night works to backfill the central pier and removing the existing concrete walkway
Zone 2 (from East of Campana Road to the SH20 Interchange)
-
Completion of drainage line installation throughout Zone 2
-
Demolition of former gantry foundations continues
-
Placing of subgrade improvement layer and completing box cuts
-
Installation of subsoil drainage continues
Utilities (throughout the site)
-
The new power transformer at Orrs Road is live after a successful shut-down on Saturday 10 Oct.
-
The section between Orrs Road and Campana Road has changed over from old to new power network.
-
Vector has provided a temporary power generator for a number of customers during the shut-down.
-
The common service trenching crew continues working in the area close to SH20 on-ramp and has successfully crossed a large number of existing services with no damage.
-
Planning to lay service ducts from Pukaki Creek Bridge to Orrs Road on the north side of SH20B from next week.
At night (all zones from 9pm to 5am, Sunday to Thursday)
There will be no through traffic from the SH20 Interchange to the Tom Pearce Drive roundabout. Please follow the posted detour signs on SH20B.
People on foot, bikes and residents will still have access.
The road will be under either stop/go or full road closure traffic management
-
Trenching works for drainage in the verge are ongoing.
-
The main focus of nightshift is continuing with asphalt pavement replacement along the existing carriageway.
Safety
SH20B has introduced the following safety measures to protect all road and shared path users including two temporary signalised road crossings for people on foot and on bikes:
-
All traffic must turn left both into and out of properties and side roads. Manukau Memorial Gardens is exempt from left-turn movements
-
Vehicles turning into driveways and side roads on the southern side must watch for bikes and foot traffic on the temporary shared cycle and walking path
-
Night time detours will likely be in place from Sunday to Thursday between 9pm and 5am. Please follow the posted detour routes
-
The speed limit for SH20B is 50kph from Manukau Memorial Gardens to Tom Pearce Drive, except at crossing points and coned paving areas where the speed will briefly drop to 30kph. Please drive safely and allow extra time for your journey.
Looking Ahead
An ongoing comprehensive programme of night works is in place to enable trenching for utility services and ducting at multiple locations across SH20B. Posted detours will be in place. We apologise for any inconvenience and thank you for your patience.
Please drive safely and allow extra time for your journey.
|