Intended programme: week commencing 15 June 2020 (weather dependent, therefore subject to change)

State Highway 2 & State Highway 29A: Truck and trailer movements through site access points to move construction plant and deliver materials.  No traffic delays expected. Monday to Friday, 9am – 4pm.

State Highway 29A: Eastbound and Westbound. Traffic Switch - line marking. Left and right lane closure. Sunday 14 June, 8pm – 5am.

State Highway 29A: Eastbound and Westbound. Traffic Switch - temporary barrier installation. Left and right lane closure. Monday 15 June, 8pm – 5am.

State Highway 2: Southbound between Maunganui/Girven roundabout and Exeter Street. Barrier remedial work replacing TL-2’s with D100 barriers. Left lane closure. Tuesday 16 June, 8pm – 5am.

State Highway 2 (around Maunganui/Girven roundabout): Barrier remedial work. Filling TL-2’s. Semi-Static. Wednesday 17 June, 8pm – 5am.

State Highway 2 & State Highway 29A: Site maintenance. Pothole fixing and pinning the missing pins for steel barriers. Semi-Static. Thursday 18 June, 8pm -  5am.

Advance notice of significant works

  • State Highway 29A: Eastbound and Westbound. Line removal. Left and right lane closure. Sunday 21 June, 8pm - 5am.
  • Te Maunga roundabout: Line removal. State Highway 2, Tauranga Eastern Link, Westbound left and right lane closure.  Monday 22 June, 8pm - 5am.
  • Maunganui/Girven roundabout: Line removal. State Highway 2, Southbound left and right lane closure. Tuesday 23 June, 8pm - 5am.

Long-term traffic management 

  • State Highway 2 Maunganui Rd: Northbound signalised pedestrian crossing is installed for the public to get into the underpass and access the Bayfair Shopping Centre.
  • State Highway 2 between Te Maunga intersection and Concord Avenue: Narrowed lanes and a 50km/h temporary speed restriction are in place for the duration of the project.
  • Bayfair roundabout: a 30km/h temporary speed restriction is in place for the duration of the project.
  • Matapihi Road, adjacent to the golf driving range: Narrowed lanes and a 30km/h temporary speed restriction is in place for the duration of the project.
  • Girven Road, near the Bayfair roundabout: Narrowed lanes are in place for the duration of the project and the right-turn from the Bayfair Shopping Centre car park onto Girven Road is permanently closed.
  • State Highway 29A near Baypark: Narrowed lanes and a 50km/h temporary speed restriction are in place for the duration of the project.
  • State Highway 2 Papamoa-bound slip lane at the Te Maunga intersection is permanently closed.
  • State Highway 2 Northbound slip lane turning to State Highway 29A from the roundabout is permanently closed.
Story
 

 
spacer

More information

spacer
 
 
Story

For more information on the Baypark to Bayfair Link upgrade project, contact us baylink@nzta.govt.nz