Huntly section project update - July 2019
   

Right now, it’s all about building pavement to support the new 15km four-lane highway east of Huntly.
That involves bringing in 300,000 tonnes of rock from Waikato quarries and then 42,000 tonnes of Stone Mastic Asphalt which will be applied as the final quiet surface ahead of the road opening early next year.
In the July project update we look at what’s been happening in recent months and what’s left to do – including the installation of cultural features along the route.
We also revisit the 4ha wetland, pictured right, which has taken shape at the southern end of Lake Kimiha as part of the project.
Read the July update here

Story
 
Back to top
 
Info For general enquiries or contact information about the Waikato Expressway please visit our website www.nzta.govt.nz/waikato-expressway or email waikatoexpressway@nzta.govt.nz or ‘like’ us on Facebook.
 
Twitter Facebook YouTube
 
 
 
© 2009 – 2015 NZTA. All rights reserved. Privacy Policy | Legal disclaimer | Copyright

You have received this email because of previous communications with the NZ Transport Agency. If you no longer wish to receive these emails you can choose to unsubscribe here

If you received this email from a friend, sign up to receive this newsletter
New Zealand Government