View online |
![]() |
![]() |
TREC Tairāwhiti recovery updateIssue 31 |
![]() |
![]() |
2 October 2025 |
![]() |
![]() |
Tēnā koeThis edition brings you the latest on our recovery work across the rohe; from concrete blocks heavier than elephants arriving at Mangahauini Gorge, to planned overnight road closures on State Highway 2 (SH2) in Hawke's Bay, and the Hikuwai Bridge main build getting started. Thanks for your ongoing patience as we carry on with our mahi with local contractors and hapū kaitiaki by our side. |
![]() |
![]() |
Hikuwai bridge build beginsIn an exciting milestone for State Highway 35 (SH35) communities, the main Hikuwai Bridge build is getting underway after the successful completion of enabling (early) works. If you're driving north of Tolaga Bay, you’ll see more crews and machinery on site as work gains momentum. The replacement bridge, pictured below, will be 2-lanes wide, approximately 100m long and follow the same alignment as the old bridge. This vital connection will be stronger and more reliable for the future. TREC is delivering the build supported by main contractor CLL and local contractors. Keep up to date with project progress on our website. Artist's impression of the Hikuwai Bridge No.1 replacement. |
![]() |
![]() |
![]() |
Speaking of bridges...We’re gearing up for the next phase of recovery work at Rotokautuku (Waiapu) Bridge near Ruatoria on SH35. We’ll share more details including a start date in the next newsletter. |
![]() |
![]() |
Clearing the way: slip removal in full swingWork to remove slip material (around 50,000 cubic metres!) that initially blocked the Mangahauini River and damaged SH35 is also tracking well. Crews have removed around 8,000 cubic metres so far. Our new project signage and brochures are now out in the community - keep an eye out! If you haven’t seen them yet, you can download both from the project website. Slip material being removed at Mangahauini Gorge. |
![]() |
![]() |
![]() |
Travelling on SH2 north of Gisborne this month?Expect 24/7 stop/go traffic management in place at both of our SH2 sites - Hakanui Straight project (near Te Karaka) and Otoko Hill site M - at times throughout October. Please allow for delays of up to 10 minutes. Quick reminder: Our traffic lights are automated to let 1 direction through at a time. Driving through a red light risks a crash and throws the system out of sync, causing delays for other drivers while crews reset the timing. Thanks for helping to keep the site and other road users safe, and traffic flowing.
|
![]() |
![]() |
SH35 Rototahe flood resilience updateEnabling (early) works are progressing well with site set-up underway and installation of the first culvert (large pipe) on the western side. Local contractors Parata Contracting are making the most of the dry weather and will soon start on road widening on the western side. De-fishing was also undertaken by our ecologists this week to safely move fish away from the work area as part of our efforts to protect our environment. The highway is down to 1 lane and drivers should expect short delays when travelling through. More information. Site set up in progress at Rototahe. |
![]() |
![]() |
![]() |
Progress at Otoko Hill - Site MHere's a progress photo of work at Site M on Otoko Hill (SH2) where crews are repairing an underslip beneath the highway. This site will have traffic lights in place throughout October as it's down to one lane while work is underway.
|
![]() |
![]() |
![]() |
Culverts, bulk fill and a traffic switch: Hakanui upgrade in full swingAt 1.8 metres wide, new culverts (large pipes) being installed at the Hakanui Straight project site, near Te Karaka, are built to handle serious water. Hard to miss right now, soon the culverts will be buried, quietly doing the heavy lifting to keep the highway dry and flood resilient. Three culverts totalling 118m long will be installed under the highway over the next month. Later this month, traffic will move onto a new road alignment, so crews can finish placing the culverts under the highway. Along with the culvert work and a swale (a shallow, planted channel that slows and filters stormwater), crews are removing vegetation and the top layer of soil on the southern side of the highway. This step, called ‘stripping’, prepares the ground for bulk fill - the material we’ll use to raise the highway by around 3 metres. A culvert being installed at the Hakanui Straight project. |
![]() |
![]() |
![]() |
SH2 overnight full road closures (Devil's Elbow, Hawke’s Bay)From Sunday 16 November to Friday 5 December full overnight road closures will be in place on SH2 in Hawke's Bay between Waikoau Hill, south of Tūtira, and Aropaoanui Road for 3 weeks. These will be from 9pm to 5am, Sunday to Thursday (5 nights each week). If you’re travelling between Gisborne and Napier please allow enough time to make it to a closure point before 9pm during those 3 weeks. SH2 Hawke's Bay closure map. |
![]() |
![]() |
![]() |
State highway snapshotBelow is a snapshot of construction works either underway or coming soon. You can also view completed, current and future work sites on our interactive map. Here are some of the construction terms we use:
SH2 underway (link to Otoko map and web page)
SH35 underway
SH35 coming soon
|
![]() |
![]() |
![]() |
Whakapā mai – Get in touchIf you spot an issue at a work site after hours, call 0800 4 HIGHWAYS (0800 444449). Sign-up to receive these regular newsletters:
Local road network Gisborne District Council is responsible for local roading recovery projects. More information. |
![]() |
|
|