Earthworks at the Aviation Security Gate area on Puhinui Road

Story
 
Story

State Highway 20B Early Improvements Update

8 May 2020

Kia ora koutou,

State Highway 20B Project Updates keep you up to date with project progress and upcoming physical works.

What we did last week (27 April – 4 May)

• Trenching and laying drainage pipes for the culvert extension outside Manukau Memorial Gardens
• Earthworks at multiple locations between the Auckland Airport Aviation Security Gate (east of the public aircraft viewing areas) and Campana Road
• Service location works throughout the site
• Fencing installation for fuel line protection on the southern side of Waokauri Bridge
• CCTV cameras near Orrs Road become operational to provide coverage of traffic flows and site works
• Mobile lighting units deployed to test efficiency prior to future lighting upgrade works

Activities for this week (4 – 11 May)

• Outfall pipe works and vegetation clearance on the eastern side of the Manukau Memorial Gardens 
• Provision of temporary car parks for mourners outside the Manukau Memorial Gardens
• Removal of the stone wall forming the old entry into the Manukau Memorial Gardens
• Continued earthworks at multiple locations between the Auckland Airport Aviation Security Gate and Campana Road
• Continued fencing installation for fuel line protection on the southern side of Waokauri Bridge
• Service location works throughout the site
• Removal of the stock fence from Campana Rd to Pukaki Creek and installation of temporary pedestrian fencing

What’s happening next week (11 - 18 May) 

Please note that these works are weather dependent and subject to possible delay.

• Continued outfall drain works and vegetation clearance on the eastern side of the Manukau Memorial Gardens

• Continued earthworks at multiple locations between the Auckland Airport Aviation Security Gate and Campana Road
• Service location works throughout the site
• Removal of existing street lights from Pukaki Creek to Orrs Rd and deployment of mobile lighting units
• Commence storm water drainage between Campana Rd and Pukaki Creek
• Commence earthworks and service locations at public viewing platforms

Looking Ahead

In the coming months we plan to carry out some utility services works by trenching across Puhinui Road at night, when traffic flows are lightest.

Safety

The residents in Campana and Prices Roads will see an increase in truckactivity between 7am and 7pm. Please be mindful of these truck movements and ensure children are supervised when using the roads.

The speed limit is 50kph. Please drive safely and allow extra time for your journey.

Story
 

 
Story

COVID-19 Updates

Alert Level 2 and SH20B


For the first three days of Alert Level 2, Waka Kotahi NZ Transport Agency will have a daytime moratorium (temporary stoppage) on planned works across the State Highway network in urban Wellington and Auckland.

This will help manage traffic demand, as public transport services are expected to have reduced capacity because of physical distancing requirements, and more people may opt to travel by private vehicle.

Until we know how the network will perform, we are taking a cautious approach to ensure our planned works don’t add any further delays.

We are proposing three days in Auckland and Wellington to initially see how travel patterns settle. It may be we have plenty of capacity in the overall transport system.

If we experience no issues on the network, we will look to end the moratorium before the three days is up.

Story
 

 
Story

Contact us

If you have any questions regarding the SH20B Early Improvements project, please call us at 0800 796 796 or email sh20B@nzta.govt.nz.

Story
 

 
spacer

Project overview

spacer
 
 
Story

Waka Kotahi NZ Transport Agency and Auckland International Airport Limited are upgrading State Highway 20B for better and more reliable travel options with a new shared path and additional priority lanes between Pukaki Creek Bridge and State Highway 20.

This project will integrate with improved transport facilities within the airport precinct along SH20B and at the upgraded Puhinui Station Interchange.

The project is the first step of the Southwest Gateway programme to provide better public transport, walking and cycling facilities with safer and more efficient freight movements to, from and around Southwest Auckland.

Fulton Hogan undertakes this work on behalf of Waka Kotahi.

Key early improvements on State Highway 20B to be delivered by 2021 include:

  • A safe place for people to walk and ride bikes
  • Safety improvements including central median barrier protection, improved lighting and a reduced speed
  • Improved pavement, drainage and stormwater treatment
  • Two improved intersections at Campana Road and Manukau Memorial Gardens.