After three weeks of night closures, repairs to the underslip on SH2 Remutaka Hill are progressing well.
As of 22 October, nine out of fifteen piles are complete and two more piles are expected to be installed before the start of the long weekend. Our crews have utilised the closures for other maintenance activities such as pothole repairs, barrier renewals, drainage repairs, asphalt resurfacing, sign installation, and debris removal.
The Remutaka Hill road will remain OPEN Sunday 27 October night for Labour Day. Nightly closures will resume on Monday 28 October at 9pm. Booking requests for the Monday 28 night closure must be made by 4pm on Friday 25 October.
|