Steady progress as Te Ahu a Turanga enters 2nd construction year
Now into its second year of construction, the Te Ahu a Turanga: Manawatū Tararua Highway is making good progress despite recent challenges from an extremely wet finish to 2021 and the arrival of Omicron to the region.
Earthworks crews had to down tools for three weeks in December as torrential rain battered Palmerston North but they have since made up for it with some record-breaking days, including moving more than 100,00 cubic metres of earth in one week and more than 20,000 cubic metres in a single day.
More than 2,000,000 cubic metres of earth has been moved to date and the team is on track for moving half of the project’s total earthworks this year. A 90T excavator has been added to the machinery line-up and scrapers are running in all but one of the earthworks zones.
At the eastern end of the alignment, the public can see the completed Cut 30 and partially completed Fill 21 from the current highway in Woodville. Further uphill, Cut 28 has commenced, and machinery can be seen on the skyline, bringing the first of 1.2M cubic metres of material downhill to Fill 20.
When finished, this cut will be around 50 metres deep. Pine trees in this area have been removed and a permanent treatment pond has been excavated for use as temporary storage for construction water.
There continues to be a lot of construction activity to see from the temporary carpark by the entrance to the Manawatū Gorge Walk. At the Parahaki Bridge site, piling for one of the bridge’s three piers is completed and a retaining wall is being built for the third pier on the KiwiRail side of the Manawatū River.
Nearby at the Eco Bridge site, work has begun on a causeway - a highly engineered embankment to form a continuous crane pad. Proof bores have been drilled and the first of eight dewatering bores have been installed. Dewatering bores are being used to help manage high artesian water pressure.
Access tracks from Saddle Road into the project area are nearing completion, which will make it easier for construction machinery to access the Eco Bridge site and the largest cuts and fills on the project.
On the landscaping front, we will be planting at three farm sites this year, and over 600,000 native plants are being cultivated. Animal and plant pest control continues in our existing ecological offset sites.
The project’s workforce is at near full capacity for the season with around 250 people on the job. The project is also providing work for 40 local businesses which are subcontracted for specific services, including concrete cutting, forestry, scaffolding, traffic management, pest control and more.
And like the rest of the country, the project is doing all it can to keep our people safe amid the COVID-19 outbreak. Stringent health and safety measures have been in place for some time, yet, despite the best plans and extreme care taken by staff, there have recently been COVID-19 cases onsite. Those affected have followed the appropriate isolation and testing procedures and have been supported by the project’s Wellbeing Team.
We have been prepared for COVID-19 to have an impact on our region and our project and now is the time when we must continue to do everything possible to put the health and wellbeing of our people first.
To view the latest flyover with commentary from Construction Manager Mike Cassaidy, go to www.nzta.govt.nz/projects/te-ahu-a-turanga/
|