Manawatū-Whanganui state highway planned roadworksSaturday 24 January to Friday 30 January |
|
23 January 2026 |
Kia ora,Welcome to the latest Manawatū-Whanganui state highway planned roadworks update. Below is this week’s list of upcoming planned works on state highways in the region. Some of our state highways are busy with traffic this summer, so give yourself plenty of time to reach your destination, and keep up to date with planned works via Journey Planner. |
||
Upcoming roadworksState highways with scheduled works this week:
Before you travel on our state highways, check Journey Planner or Facebook for the latest information. Dates in this update may change at short notice due to weather or other unforeseen factors, and other less disruptive state highway works may not be listed in this newsletter. Information current as at 12pm on Friday 23 January 2026. |
||
State Highway 1SH1 north of Taihape: Road rebuild works are underway near the intersection of Spooners Hill Road. Works are ongoing until Monday 2 February, 6am to 6pm, Monday to Saturday. Stop/go traffic management and a 30km/h speed limit is in place, with delays of up to 25 minutes at peak travel times. More information. SH1 Foxton: Road rebuild and drainage works will take place near the intersection of Wall Road from Tuesday 10 February to Friday 13 March. Work will run from 6pm to 6am under stop/go traffic management, with 5-minute delays expected. |
||
State Highway 2SH2 Mangatainoka: Road rebuild and drainage works are underway at Mangatainoka, near the Ruawhata Road. Works are ongoing until Tuesday 3 February, 6am to 6pm. Stop/go traffic management and a 30km/h speed limit is in place, with delays of up to 5 minutes. More information. SH2 Makirikiri Bridge: Patch repairs will take place on Makirikiri Bridge south of Dannevirke from Tuesday 27 January to Saturday 31 January. Work will run from 6pm to 6am under a mixture of stop/go and stop/stop traffic management, with delays of up to 20 minutes expected. SH2 Mangamaire: Maintenance work is underway at the SH2/Tutaekara Road intersection until 6pm on Friday 23 January. Stop/go traffic management is in place with delays of up to 10 minutes. SH2 Woodville: Asphalt resurfacing works are planned for Vogel Street, Woodville from Sunday 8 February to Monday 16 March 2026. This work will be completed in 2 phases, under a full night-time closure, 6pm to 6am. Expect changing traffic management and detour routes, including during the day. More information. |
||
State Highway 3SH3 Whakarongo: A road rebuild will take place on SH3 between Roberts Line and Stoney Creek Road from Sunday 25 January to Thursday 5 February. Night works will run Sunday to Friday from 6pm to 6am, with a daytime shift expected between 9am and 3pm on Monday 2 February. Stop/go traffic management will be in place, and delays of up to 10 minutes are expected. |
||
State Highway 4SH4 Raetihi: Road rebuild and drainage works are underway on Parapara Road, Raetihi, between Seddon Street and Alexandra Road. Works are ongoing to Monday 9 February, 6am to 6pm. Stop/go traffic management and a 30km/h speed limit is in place, with delays of up to 15 minutes. More information. |
||
State Highway 43SH43, Taumarunui: Work on the Pongahuru Stream Bridge was delayed this week due to bad weather. The bridge will now be closed to agricultural and heavy vehicles from 7am Wednesday 28 January to 12pm on Saturday 31 January. Cars and other light vehicles can still use the bridge during the closure. A signposted detour is in place via SH4, Ohura Road, and Mangaparo Road, adding about 17 minutes to travel time to and from Taumarunui. Stop/go controls are in place at the bridge, with delays of up to 5 minutes for light vehicles during the closures. All work on the bridge is expected to be completed by the end of February. More information. |
||
State Highway 57SH57 Shannon: A road rebuild will take place on SH57 north of Shannon from Tuesday 3 February to Friday 13 March. Night works will run from 6pm to 6am each day with stop/go in place and delays of 10 minutes. A temporary 30km/h speed limit will be in place outside of work hours. SH57 Levin: Drainage works will take place on SH57/ Arapaepae Road from Monday 9 February to Friday 13 February. Works will run from 7:30am to 5pm with stop/go in place and delays of 5 minutes. |
||
Other works in January-February 2026A range of resealing road maintenance sites are planned across our state highways this summer. For example, after resealing works are complete on SH1 and SH57, crews plan to move to SH2 south of Norsewood. Please follow temporary traffic management and expect delays at resealing sites. |
||
More information |
||
|
Please be aware that there may be other less disruptive state highway works not listed in this newsletter. Roadworks listed in this newsletter may be postponed due to rain or other factors that disrupt the weekly schedule. Check the NZTA Journey Planner for the latest travel information and journey times before starting your journey: journeys.nzta.govt.nz. For more information on the Manawatū-Whanganui state highway maintenance programme, contact us at info@nzta.govt.nz or via 0800 4 HIGHWAYS (0800 444 449). Visit our website www.nzta.govt.nz/manawatu-whanganui-maintenance |
||
|
|
||||||||||||||||
|