Full closure speeds up work in Duncan Maclean Link
The full closure of Duncan Maclean Link last weekend enabled us to complete the two raised table crossings at the intersection with St Lukes Road. This means that the major works there have been reduced from two weekends to one. We still have to complete footpaths, landscaping, signage and a general tidy-up to finish work in Duncan Maclean Link. We thank you for your patience while this essential work was done and the road was closed.
Work continues on other parts of the project. We have the last raised table crossing to build on the weekend of 14-17 February, this one on the westbound motorway on-ramp.
Below: Concrete pour for the raised table crossings at Duncan Maclean Link
|