Northern Underpass & Shared Path
We're working in the area around Parliament Street, Pharazyn Street and Bridge Street at the moment. This work includes constructing the new shared path beneath the Normandale Bridge, and across the Greenaway reserve.
At Easter we will complete the underpass beneath the rail near Parliament Street. We completed work to prepare for this at Christmas. Building the underpass (and restoring the rail above) will take five days, working day and night, from the evening of Thursday 9 April through to Tuesday 14 April.
There are no scheduled train services on the Melling line during Easter, and buses will replace trains on Tuesday 14 April, while the underpass is built and the track is reconnected. More information on bus replacements will be published on the Metlink website.
To complete this work, we need to close the road on Parliament Street. Vehicle access for residents will be maintained, otherwise please follow the detour on Laery Street and Herbert Street.
We know that this type of work can be disruptive, especially during holidays and weekends. Thank you for your patience.
|