View online | Unsubscribe
 
banner

Image
Story

(Photo by Karol Brooks) The western section of the Shared Use Path at Waokauri Bridge was lifted into place on Thursday night, with the eastern side due to be installed in the coming week. When works are complete, cyclists and walkers will enjoy reliable and safe access the full length of SH20B.

Story
 
Story

State Highway 20B Early Improvements Update

13 November 2020

Kia ora koutou,

State Highway 20B Project Updates keep you up-to-date with project progress and upcoming physical works on State Highway 20B (SH20B).

 

Story
 

 
Story

Weekend closure from 9pm today (Friday 13 November) to 5am Monday 16 November

NO THROUGH-ACCESS TO AUCKLAND AIRPORT

Waka Kotahi will close State Highway 20B (SH20B) to through-traffic between the Tom Pearce/SH20B roundabout and the SH20 interchange for two consecutive weekends in November to allow essential work to proceed that cannot take place safely during normal working hours. Detours will be in place. These weekends are: 

• 9pm, Friday 13 November to 5am, Monday 16 November
• 9pm, Friday 20 November to 5am, Monday 23 November
.

Manukau Memorial Gardens will remain open, and resident/business access to Campana and Prices Roads will be available from the eastern approach to SH20B. Access to cyclists and people on foot will also be maintained throughout the weekend.

We apologise in advance for any inconvenience. 

BUS ROUTE 380

During the closures the 380 Airporter bus service will be detoured along alternative routes. Some delays can be expected during this time. Please plan ahead and use the journey planner for up-to-date travel times.

Story
 

Image
Story

Public consultation on a safer speed limit and a proposed bus/T3 lane bylaw ended on Sunday 8 November 2020.

Story
 
Story

PUBLIC CONSULTATION CLOSED

The four-week long public consultation is now closed.

Waka Kotahi received more than 100 responses and feedback during the public consultation process on a new speed limit and a new bylaw on bus/T3 lanes along SH20B. 

We will keep you updated with the next steps on 20Connect.

Thank you for your interest and feedback.

Story
 

 
Story

Project progress

Activities next week (16 - 19 November)

Please note that these works are weather dependent and may be delayed.

During the day (from 7am to 6pm)

Zone 1 (from Pukaki Creek Bridge to East of Campana Road)

  • Westbound traffic moved onto the widened section near Campana Road to allow for granular infill on the east-bound lane.
  • Preparation works on the shared use path base from the Aviation Security gate to Campana Road
  • Shared use path from Pukaki Creek Bridge to the viewing platforms has been relocated to a temporary position for weekend closure works
  • Drainage crossing near Pukaki Creek Bridge to be completed.

Waokauri Bridge

  • The eastern Shared Use Path bridge section is ready to be lifted into place this week
  • Duct brackets will be installed on the south side of the bridge

Zone 2 (from East of Campana Road to the SH20 interchange)

  • Asphalt is being laid offline between Waokauri Bridge and the State Highway 20 Interchange
  • Completion of preparation works for subgrade improvement layer to the east of Prices Road
  • Pouring kerb and channel concrete east of Prices Road
  • Placement of barriers on top of the L-wall at Manukau memorial Gardens
  • Removal of temporary barriers and installation of concrete barriers.

Utilities (throughout the site)

  • Chorus hauling the cables between Manukau Memorial Gardens and the SH20 Interchange  
  • Continuing laying the service ducts in the area close to Waokauri Bridge.

At night (all zones from 9pm to 5am, Sunday to Thursday)

  • Night time drainage works to verges and road crossings are ongoing
  • Continuing with asphalt pavement replacement along the existing carriageway.

There will be no through traffic from SH20 interchange to the Tom Pearce Drive roundabout. Please follow the posted detour signs on SH20B.

Safety

SH20B has introduced the following safety measures to protect all road and shared path users including two temporary signalised road crossings for people on foot and on bikes:

  • All traffic must turn left both into and out of properties and side roads. Manukau Memorial Gardens is exempt from left-turn movements
  • Vehicles turning into driveways and side roads on the southern side must watch for bikes and foot traffic on the temporary shared cycle and walking path
  • Night time detours will likely be in place from Sunday to Thursday between 9pm and 5am.  Please follow the posted detour routes
  • The speed limit for SH20B is 50kph from Manukau Memorial Gardens to Tom Pearce Drive, except at crossing points and coned paving areas where the speed will briefly drop to 30kph. Please drive safely and allow extra time for your journey.

Looking Ahead

An ongoing comprehensive programme of night works is in place to enable trenching for utility services and ducting at multiple locations across SH20B. Posted detours will be in place. We apologise for any inconvenience and thank you for your patience.

Please drive safely and allow extra time for your journey.

Story
 

 
Story

Contact us

Please call us at 0800 796 796 or email sh20B@nzta.govt.nz if you have any questions about the SH20B Early Improvements project.

Story
 

 
spacer

Project overview

spacer
 
 
Story

Waka Kotahi NZ Transport Agency and Auckland International Airport Limited are upgrading State Highway 20B for better and more reliable travel options with a new shared path and additional priority lanes between Pukaki Creek Bridge and State Highway 20.

This project will integrate with improved transport facilities within the airport precinct along SH20B and at the upgraded Puhinui Station Interchange.

The project is the first step of the Southwest Gateway programme to provide better public transport, walking and cycling facilities with safer and more efficient freight movements to, from and around Southwest Auckland.

Fulton Hogan undertakes this work on behalf of Waka Kotahi.

Key early improvements on State Highway 20B to be delivered by 2021 include:

  • A safe place for people to walk and ride bikes
  • Safety improvements including central median barrier protection, improved lighting and a reduced speed
  • Improved pavement, drainage and stormwater treatment
  • Two improved intersections at Campana Road and Manukau Memorial Gardens.

Waka Kotahi NZ Transport Agency works to create transport solutions for all New Zealanders – from helping new drivers earn their licences, to leading safety campaigns to investing in public transport, state highways and local roads.