Intended programme for w/c 16 February 2020 (weather dependent, therefore subject to change)

SH2 & SH29A Truck and trailer movements through site access points to move construction plant and deliver materials. No traffic delays expected. From Monday to Friday. Days: 9am to 4pm.

SH2 TEL North-bound road closure, south-bound lane closure sewer relocation work/stone column work Monday 17 February and Tuesday 18 February 2020. Nights only 8 pm to 5am.

SH2 TEL lane closure stone column work Wednesday 19 February and Thursday 20 February Nights only 8pm to 5am.

SH2 Maunganui Road South-bound left lane closure traffic switch Sunday 23 February. Night only 8pm to 5am.


Advanced notice of significant works
SH29A both directions
lane closure for concrete barrier removal Sunday 8 March to Thursday 12 March. Night Only 8 pm to 5am, and Sunday 15 March to Thursday 19 March. Night only 8pm to 5am.

Long-term traffic management
• State Highway 2 Maunganui Rd NB signalized pedestrian crossing is installed and active for the public to cross the NB traffic to get to the underpass and access Bayfair.
• State Highway 2 between Te Maunga intersection and Concord Avenue - narrowed lanes and a 50km/h temporary speed restriction are in place for the duration of the project.
• SH2 Maunganui Rd SB two lanes approaching the Bayfair roundabout have been split to create a work zone in the middle so motorists coming to Bayfair from the city need to use the left lane to access the Bayfair entries on SH2 Maunganui Rd.
• Bayfair roundabout – a 30km/h temporary speed restriction is in place for the duration of the project.
• Matapihi Road, adjacent to the golf driving range – narrowed lanes and a 30km/h temporary speed restriction are in place for the duration of the project.
• Girven Road, near the Bayfair roundabout - narrowed lanes are in place for the duration of the project and the right-turn from the Bayfair Shopping Centre car park onto Girven Road is permanently closed.
• SH29A near Baypark – narrowed lanes and a 50km/h temporary speed restriction are in place for the duration of the project.
• SH2 Papamoa-bound slip lane at the Te Maunga intersection is permanently closed.
• SH2 Northbound slip lane turning to SH29A from the roundabout is permanently closed.

Story
 

 
spacer

More information

spacer
 
 
Story

For more information on the Baypark to Bayfair Link upgrade project, contact us baylink@nzta.govt.nz

Visit our website www.nzta.govt.nz/baylink