Intended programme for w/c 9 February 2020 (weather dependent, therefore subject to change)
SH2 & SH29A Truck and trailer movements through site access points to move construction plant and deliver materials. No traffic delays expected. From Monday to Friday. bays: 9am to 4pm.
SH2 east-bound between Bayfair and Te Maunga roundabout left lane closure for stone column works Monday 10 February to Thursday 13 February. Nights: 8pm to 5am.
SH2 Maunganui Road layout changes near Bayfair roundabout from Monday 10 February 8pm to 5am. Temporary traffic lights for pedestrians to cross the city-bound lanes go on live from Wednesday 12 February. See story below.
SH29A road closure between the Baypark and Te Maunga roundabouts for stone column works from 8pm Friday 14 February to 5am Monday 17 February. Detours will be in place.
Advanced notice of significant works
SH2 TEL one-way road closure between Sandhurst Drive and Te Maunga roundabout for sewer relocation and stone column work Monday 17 February to Tuesday 18 February. Night only 8pm to 5am.
SH2 TEL one-way road closure between Sandhurst Drive and Te Maunga roundabout for stone column work Wednesday 19 February and Thursday 20 February. Night only 8pm to 5am.
SH2 Maunganui Road Bayfair roundabout east-bound right lane closure for drainage works in the middle of the roundabout. Sunday 16 February to Thursday 20 February. Night Only 8 pm to 5am.
SH29A road closure between the Baypark and Te Maunga roundabouts for stone column works from 8pm Friday 21 February to 5am Monday 24 February. Detours will be in place.
Long-term traffic management
• State Highway 2 between Te Maunga intersection and Concord Avenue - narrowed lanes and a 50km/h temporary speed restriction are in place for the duration of the project.
• SH2 Manganui Rd SB two lanes approaching to Bayfair roundabout has been split to create an work zone in the middle, so the people coming to Bayfair from city needs to use left lane to access the Bayfair entries on SH2 Manganui Rd.
• Bayfair roundabout – a 30km/h temporary speed restriction is in place for the duration of the project.
• Matapihi Road, adjacent to the golf driving range – narrowed lanes and a 30km/h temporary speed restriction is in place for the duration of the project.
• Girven Road, near the Bayfair roundabout - narrowed lanes are in place for the duration of the project and the right-turn from the Bayfair Shopping Centre car park onto Girven Road is permanently closed.
• SH29A near Baypark – narrowed lanes and a 50km/h temporary speed restriction are in place for the duration of the project.
• SH2 Papamoa-bound slip lane at the Te Maunga intersection is permanently closed.
• SH2 Northbound slip lane turning to SH29A from the roundabout is permanently closed.
|