Roadworks update

SH2 Remutaka Hill Road

 
spacer

Friday, 17 November 2023

spacer

 

Kia ora

Below are the dates for the upcoming 6 months of SH2 Remutaka Hill night-time maintenance closures. These closely align with the closure schedules of the past two years and avoid known dates for major events.

There will be 31 nights of closures between January to June 2024 - six block closures of five nights each and one Sunday night only closure.

The schedule includes more nights than usual to account for an extensive safety improvements project which will include additional side barriers, motorcycle safety rails under existing barriers, and improved road signage and markings.

Please note the May bookings have been updated from those advertised in the newspapers this week. The updated schedule will be in new advertisements published in next week’s papers.

Schedule

Nights         Start 9pm                  Finish 4am

1 night         Sun 14 Jan                  Mon 15 Jan

10 nights      Sun 10 March              Fri 15 March

                   Sun 17 March              Fri 22 March

5 nights        Sun 14 April                Fri 19 April

10 nights      Sun 19 May                 Fri 24 May

                   Sun 26 May                 Fri 31 May

5 nights        Sun 16 June                Fri 21 June

Light vehicles can be escorted at intervals across the hill behind a pilot vehicle. Bookings are essential and should be made using the form below.

Remutaka Hill Closure Escort Booking Form

Please direct any additional inquiries to customer@wta.nzta.govt.nz

People wanting to cross the hill during the closure should book in advance for a place on the escorted crossings.

  • For Sunday night, please book by 4pm Friday
  • For Monday through Thursday nights, please book by 4pm each day for that night

Regular Timetable

10.30pm Hutt to Featherston 

11.30pm Featherston to Hutt

12.30am Hutt to Featherston

01.30am Featherston to Hutt

Please note there will be fewer crossings when road resurfacing work is planned. We'll let you know.

Numbers are strictly limited and travellers turning up without a booking risk being turned away or having to wait at the closure point until the next crossing or the road opens. Any additions to an escorted crossing are at the discretion of the hill manager who must consider the safety of workers and travellers on the night.

Access will be available for 'flashing light' emergency services throughout the closures.

We understand the closures may inconvenience some road users and thank you for your patience and understanding as we carry out this essential maintenance work.

These regular night closures significantly reduce the number of disruptions at other times for road users. Road crews can complete a large amount of work safely during these closures because multiple crews can work across the hill simultaneously without disrupting traffic.