A key project milestone reached
As our crew reach the bottom of the last excavation site (Site 6), all five sites are now able to be regularly worked on simultaneously.
Construction of the retaining walls on four of the five sites has now either started, is well progressed or complete. Wall construction on the fith site is expected to start mid April. This is a major project milestone that will help construction progress as we head into the winter months.
The coming months will require several nightly road closures to complete culvert extensions across State Highway 60. More about that further on.
The team continues to work hard, with the chief focus on having two lanes open by the end of this year.
Below is an update of each of the five sites:
Site 6: The design bottom of this site was reached in March. However, the material at this foundation did not pass the strict geologists scrutineering. Further excavation was required to reach a firm enough platform before construction could start on building the retaining wall back up to road height.
Site 7: The retaining wall is complete and precast panels are being cast off-site in preparation for placement in front of the wall. Most of the rip-rap (large boulders which manage the water runoff) is complete. Following installation of the culvert, pavement works will start and placement of precast panels will be undertaken. The first night closure to undertake the culvert installation is scheduled for 3–10 May.
Site 9: The retaining wall is close to completion, following which the team will move onto pavement construction.
Site 11: The retaining wall construction is well underway (50% complete), with 12 rock baskets completed currently.
Site 13: The team have finally reached the bottom of this, the most challenging site, and the first layer of baskets have been installed.
|