First major concrete pour for Bay Link project
A major milestone was reached last month with the first concrete pour at the Baypark end of the project. The focus in this area has shifted from below-ground improvements to above-ground construction.
Concrete has been poured for one of the two rail impact walls. These are designed to protect the walls supporting the new road over the railway from collapsing if they were ever hit by trains. The first structural wall used 300m3 of concrete – 60 truck loads.
Other retaining walls are also taking shape in the area, forming the sides of the embankments. Two techniques are being used to build the 18 Mechanically Stabilised Earth (MSE) walls; sandbags with reinforced high-density plastic grid, and concrete blocks with steel reinforcing ladders.
A wall made up of a grid of sandbags is emerging and can be seen as you approach Te Maunga roundabout from Papamoa. About 500 sandbags can be filled and stacked each day, covering around 33m2 of the wall face.
Reinforced high-density plastic grid is then used to hold the bags in place and strengthen the structure as it progresses. Once completed, approximately 22,000 sandbags will have been used to complete the 1320m2 wall.
Construction of a 10m high retaining wall is underway near the intersection of SH2 and SH29A. About 21,000 concrete blocks, sourced from a Morrinsville
manufacturer, have arrived on site.
Workers have been busy removing 4500m3 of earth (totalling about 225 truck movements), leaving behind a deep excavation where this new retaining wall will be constructed before an embankment made of pumice is built on top.
The concrete block wall construction will involve stacking the blocks on top of each other and using 11,600 high grade steel reinforcing ladders laid horizontally behind the wall.
The stone column ground improvement beside the Te Maunga roundabout is nearing completion, with 4100 stone columns installed in the area to date.
|