SH29A closure this weekend

State Highway 29A between Baypark and Te Maunga roundabouts will be closed during this weekend to allow for stone column ground improvement works to be carried out.

The road will be closed from 9pm Friday 22 March to 4am Monday 25 March, and depending on progress, it could also be closed from 9pm Friday 29 March to 4am Monday 1 April.

Signposted detours will be in place. This work was postponed in December 2018 due to a lightning storm.

Story
 
Image

 
Story

Week commencing 17 March 2019

Intended programme for next week (weather dependent, therefore subject to change)

Owens Place  A contra flow remains in place during pavement works in the verge next to HomeZone. No traffic delays are expected. Sunday 17 March to Saturday 23 March 2019. Nights & days: ongoing.

Matapihi Road Lane closures will be in place while the road layout is changed. Traffic will be moved onto the new section of road (southern side) between SH2 and the rail line, to enable the work area on the northern side to be extended. Minor traffic delays expected. Sunday 17 March and Monday 18 March 2019. Nights: 7pm to 6am.

SH2 & SH29A Truck and trailer movements through site access points to move construction plant and deliver materials. No traffic delays are expected. Monday 18 March to Friday 22 March 2019. Days: 9am to 4pm.

SH2 - TEL Semi statics will be deployed northbound during street light relocation. Wednesday 20 March 2019.Nights: 9pm to 6am.

SH2 – Jackson Street Bayfair Shopping Centre entrance, closest to the Bayfair roundabout, closed during water main relocation. (Other entrances are unaffected.) Wednesday 20 March 2019.Nights: 7pm to 6am.

SH2 - southbound Lane closures and semi statics required during street light relocation in the verge, near the Bayfair roundabout. Thursday 21 March 2019.
Nights: 7pm to 6am.

SH29A closure Closure of SH29A between the Te Maunga and Baypark roundabouts to install stone columns. A sign posted detour will be in place.
Traffic delays are expected. Friday 22 March to Monday 25 March 2019.Nights and days: 9pm Friday to 5am Monday.

Advanced notice of significant works
SH2 – Jackson Street Bayfair Shopping Centre entrance, closest to the Bayfair roundabout, closed during water main relocation. Monday 25 March 2019. Nights: 7pm to 6am.

SH29A closure (Contingency) Closure of SH29A between the Te Maunga and Baypark roundabouts to install stone columns. A sign posted detour will be in place. Traffic delays are expected. Friday 29 March to Monday 1 April 2019.Nights and days: 9pm Friday to 5am Monday.

SH2/SH29A Semi static closures required between Te Maunga and Bayfair roundabouts, and Te Maunga and Baypark roundabouts, while drilling rigs are moved. Minor traffic delays expected.  Sunday 31 March 2019. Night: 9pm to 10pm.

Long-term traffic management
• State Highway 2 between Te Maunga roundabout and Concord Avenue - narrowed lanes and a 50km/h temporary speed restriction are in place for the duration of the project.

• Bayfair roundabout – a 30km/h temporary speed restriction is in place for the duration of the project.

• Matapihi Road, adjacent to the golf driving range – narrowed lanes and a 30km/h temporary speed restriction is in place for the duration of the project.

• Girven Road, near the Bayfair roundabout - narrowed lanes are in place for the duration of the project and the right-turn from the Bayfair Shopping Centre car park onto Girven Road is permanently closed.

• Access onto State Highway 2 / Maunganui Road from Exeter Street is closed for about 18 months. Resident only access.

• SH29A near Baypark – narrowed lanes and a 50km/h temporary speed restriction are in place for the duration of the project.

Story
 

 
spacer

More information

spacer
 
 
Story

For more information on the Baypark to Bayfair Link upgrade project, contact us baylink@nzta.govt.nz

Visit our website www.nzta.govt.nz/baylink