From 8 to 19 April on weekdays, road closures are planned on Queen Charlotte Drive between the Picton Lookout and Shakespeare Bay between 9am to 3pm, with openings on the hour every hour. There will be delays of up to 10 minutes between 7am to 9am at this location. These closures are for Port Marlborough to undertake logging operations and the removal of wilding pines and wattles.
There are increased works along the length of Queen Charlotte Drive with multiple recovery sites under construction. These works will be under stop/go traffic management, please expect delays.
Crews have been working on the construction of a MSE (Mechanically Stabilised Earth) wall and associated drainage upgrades on Queen Charlotte Drive (approximately 1.7km from the SH6/Havelock turnoff) near Cullen Point, Mahakipawa Hill.
Last week anchor drilling and the installation of wailers was carried out at this site. This week and next week crews will start building the downstream section of the wall.
Works to install a new culvert and repair the road are continuing, just prior to Moenui Road, when travelling from Havelock. Last week backfilling and compacting was carried out. This week two further sections of the culvert have been installed. Next week works will continue to install the remaining sections of the culvert upstream.
The construction of two railway iron walls is being carried out approximately 1.9km and 2.1km past Tepuia Heights, on Queen Charlotte Drive when travelling towards Picton. Last week and this week preparations have been made for sealing. This week pavement reinstatement has been undertaken. The driving of railway irons and tie backs will be completed next week at the first site 1.9km from Tepuia Heights. Users of the Link Pathway will be guided through these sites by traffic management.
Works are being undertaken 750m past The Grove Jetty, when travelling towards Picton to complete drainage upgrades and repair a dropout. Last week and this week backfilling works and drainage works have been undertaken. Next week drainage works will continue with surfacing works to be carried out at this location shortly after.
Works continue at a new retaining wall site, 450m past Aussie Bay. Last week crews installed a new culvert and site rail to the wall. Next week kerb preparation works are scheduled.
Works to realign the road and repair a slip continue 70m past Governors Bay when travelling towards Picton. Last week crews drilled anchors on the slope below and prepared to lay mesh. This week crews continued to lay mesh in preparation to shotcrete the slope of the slip next week. They will also carry out earth works to create a retreat, on the uphill side of the repaired slip site.
A third railway iron site, 450m before Moenui Road, when travelling towards Picton is scheduled to start, once works are completed on the two railway iron walls near Tepuia Heights.
Please note there will be increased truck movements while these works are being carried out. Please plan ahead for delays.
Please keep to the reduced temporary speed limits when you're travelling through our worksites to ensure the safety of crews and road users. We thank you for your patience.
|