Waka Kotahi NZ Transport Agency

SH25/SH25A Thames-Coromandel

16 October 2023


The column and pier for B and C
 

Beams waiting to be lifted into place

SH25A Taparahi - decking the way

The first stage of the bridge deck construction has started. The team installed 3 spans of the girders last week and over the weekend. The girders are the long steel beams that span between the abutments and piers, and support the bridge deck.

The girders are spliced together in combinations of 18m and 29m sections and then lifted into place. There is also steel bracing between the steel girders which is progressively installed as the team work their way across from abutment A (the western abutment) to abutment D (the eastern abutment)

This week the team is focused on preparing the girders for the final span of Pier C to Abutment D. The lifts are very dependent on the weather. If the wind is too strong it is not safe to lift the girders into place.

See below some more activities undertaken last week on and off site:

Abutment A: The wingwalls were finalised and are ready to be poured this week.

Abutment D: The wingwall steel reinforcement has been tied and are now ready for the concrete pour this week.

Pier B and C: Plinths were poured and the third span was lifted in place over the weekend.

Offsite: The final 3 steel girders are due to be despatched from Napier and arrive on site this week. In the meantime, fabrication continues on the 138 concrete pre-cast panels (which will be placed on the steel beams to form the bridge deck) and 52 pre-cast side barriers.

 


 

Look after our road workers

Waka Kotahi is committed to a safer Aotearoa New Zealand where no one is killed or seriously injured on our roads. This includes keeping our road workers safe - the people working on the country's roads who are doing their best to make them safer for you.

There's no excuse for abusing people as they go about their job.

Be kind, be respectful, and be careful around road workers. Just like you, they deserve to get home at the end of the day.

Watch: Look after road workers, they're part of your community.

 

 

Tairua and Takatakahia bridge strengthening

SH25 and SH25A maintenance and recovery work

State highway road maintenance and recovery work is underway at various locations around the peninsula. 

If you’re out on the road, please keep an eye out for our traffic management and crews - and don't forget to give them a wave.

 



 

More information

 
 

If there's something you'd like to know more about, or you have a question, we'd love to hear from you. Contact us at coromandel@nzta.govt.nz and we'll include the answers in upcoming issues.

Visit our website www.nzta.govt.nz/thames-coromandel

SH25A project information sheet