Intended programme for this week (weather dependent, therefore subject to change)

SH29A both directions lane closure for concrete barrier removal, Monday 23 March to Thursday 26 March, nights only from 8pm to 5am (finishing Friday morning).

SH2 & SH29A Truck and trailer movements through site access points to move construction plant and deliver materials. No traffic delays expected. From Monday to Friday Days: 9am to 4pm.

Advanced notice of significant works

SH2/SH29A multiple lane closure for stone column CPT testing, Sunday 29 March, night only 8pm to 5am.

SH29A both directions lane closure for concrete barrier removal, Sunday 29 March to Thursday 2 April, night only 8pm to 5am (finishing Friday morning).

SH2/SH29A multiple lane closure for stone column CPT testing, Sunday 5 April, night only 8pm to 5am.

Long-term traffic management
• State Highway 2 Maunganui Rd NB signalized pedestrian crossing is installed and active for the public to get into the underpass and access Bayfair shopping center.
• State Highway 2 between Te Maunga intersection and Concord Avenue - narrowed lanes and a 50km/h temporary speed restriction are in place for the duration of the project.
• Bayfair roundabout – a 30km/h temporary speed restriction is in place for the duration of the project.
• Matapihi Road, adjacent to the golf driving range – narrowed lanes and a 30km/h temporary speed restriction is in place for the duration of the project.
• Girven Road, near the Bayfair roundabout - narrowed lanes are in place for the duration of the project and the right-turn from the Bayfair Shopping Centre car park onto Girven Road is permanently closed.
• SH29A near Baypark – narrowed lanes and a 50km/h temporary speed restriction are in place for the duration of the project.
• SH2 Papamoa-bound slip lane at the Te Maunga intersection is permanently closed.
• SH2 Northbound slip lane turning to SH29A from the roundabout is permanently closed.

Story
 

 
spacer

More information

spacer
 
 
Story

For more information on the Baypark to Bayfair Link upgrade project, contact us baylink@nzta.govt.nz

Visit our website www.nzta.govt.nz/baylink